4020 W WASHINGTON BLVD 90018
Certificate Information: 4020 W WASHINGTON BLVD 90018
- Application / Permit
- 21016-10000-16296
- Plan Check / Job No.
- B21LA11852
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Ice Cream Parlor
- Work Description
- CHANGE OF USE FROM WORSHIP HALL TO ICE CREAM SHOP AND TENANT IMPROVEMENT. COMPLY WITH THE DEPARTMENT ORDER EFFECTIVE DATE 7/7/21. PERMIT WILL EXPIRED 30 DAYS FROM ISSUANCE DATE.
- Permit Issued
- Issued on 9/21/2021
- Issuing Office
- Current Status
- Issued on 9/21/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/2/2021 | CRISTINA SALAZAR |
| Corrections Issued | 7/3/2021 | CRISTINA SALAZAR |
| Building Plans Picked Up | 8/9/2021 | APPLICANT |
| Applicant returned to address corrections | 9/10/2021 | ZAW HAN |
| Plan Check Approved | 9/14/2021 | ZAW HAN |
| Issued | 9/21/2021 | APPLICANT |
Permit Application Clearance Information
| CPC | Cleared | 7/19/2021 | RUBEN VASQUEZ |
| ZA Case | Cleared | 7/19/2021 | RUBEN VASQUEZ |
| Redevelopment Project Area | Cleared | 7/22/2021 | GISELLE CORELLA |
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2021 | CELINA MORENO |
| Sewer availability | Cleared | 7/26/2021 | CELINA MORENO |
| Community Plan Implem. Overlay | Cleared | 8/31/2021 | KYLE WINSTON |
| Food Service Establishment | Cleared | 9/2/2021 | PAWAN VERMA |
| Food establishment approval | Cleared | 9/10/2021 | LACDHS APPROVED |
Contact Information
| Contractor | Watts Builders Inc; Lic. No.: 1076049-B | 10221 S COMPTON AVE STE 101 LOS ANGELES, CA 90002 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/30/2021 | Approved | KATY RAMIREZ |
| METHANE-Rough | 11/12/2021 | Not Ready for Inspection | KATY RAMIREZ |
| Footing/Foundation/Slab | 3/2/2022 | Not Ready for Inspection | KATY RAMIREZ |
| Drywall Nailing | 5/18/2022 | Approved | KATY RAMIREZ |
| Final | 6/14/2022 | Partial Inspection | KATY RAMIREZ |
| METHANE-Final | 6/14/2022 | Approved | KATY RAMIREZ |
| METHANE-Rough | 6/14/2022 | Approved | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 6/14/2022 | SGSOV No Gas | KATY RAMIREZ |
| Smoke Detectors | 6/14/2022 | Approved | KATY RAMIREZ |
| Wood Frame | 6/14/2022 | Partial Inspection | KATY RAMIREZ |