4439 W SUNSET BLVD 90027

Certificate Information: 4439 W SUNSET BLVD 90027

Application / Permit
21016-10000-16128
Plan Check / Job No.
B21LA11719
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
TENANT IMPROVEMENT & CHANGE OF USE FROM (E) GYM TO (N) RETAIL. COMBINE 3 TENANT SUITES
Permit Issued
Issued on 10/18/2021
Issuing Office
Current Status
CofO Issued on 3/9/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/23/2021 APPLICANT
Assigned to Plan Check Engineer 7/15/2021 LAMAR DAVIS
Plans on Hold 7/23/2021 LAMAR DAVIS
Hold Released 7/30/2021 LAMAR DAVIS
Corrections Issued 7/30/2021 LAMAR DAVIS
Quality Review Completed 8/3/2021 WING SUEN
Building Plans Picked Up 8/5/2021 APPLICANT
Plan Check Approved 9/29/2021 LAMAR DAVIS
Issued 10/18/2021 APPLICANT
CofO in Progress 3/9/2022 SORIN CIRSTOIU
CofO Issued 3/9/2022 TED RIES
Permit Finaled 3/9/2022 TED RIES

Permit Application Clearance Information

Hold Cleared 7/29/2021 JASON SHEETS
Eng Process Fee Ord 176,300 Cleared 8/12/2021 CECILIO NAVARRO
Sewer availability Cleared 8/26/2021 STEVE MELGAR
"D" conditions Cleared 8/27/2021 DANIEL CORONADO
Miscellaneous Cleared 8/27/2021 DANIEL CORONADO
ZA Case Cleared 8/27/2021 DANIEL CORONADO
ZA Case Cleared 8/27/2021 DANIEL CORONADO
ZA Case Cleared 8/27/2021 DANIEL CORONADO
ZA Case Cleared 8/27/2021 DANIEL CORONADO
ZI Cleared 8/27/2021 DANIEL CORONADO
DAS Clearance Cleared 9/8/2021 EDDIE GARIN
Address approval Cleared 9/22/2021 STEVE MELGAR

Contact Information

Contractor Hoa Specialists Construction Services Inc; Lic. No.: 1026722-B 24266 WALNUT ST      NEWHALL, CA 91321
Engineer Michal,, Jerry Lee; Lic. No.: C42590 2499 ROCK VIEW GLEN      ESCONDIDO, CA 92026

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 10/27/2021 Partial Inspection SORIN CIRSTOIU
Deputy Steel/Welding 10/29/2021 Conditional Approval JONATHAN QUACH
Wood Frame 11/4/2021 Partial Inspection JONATHAN QUACH
Floor/Roof Diaphrgm/Shear Wall 11/8/2021 Partial Inspection SORIN CIRSTOIU
Deputy Wood Construction 11/10/2021 Approved SORIN CIRSTOIU
Floor/Roof Diaphrgm/Shear Wall 11/10/2021 Approved SORIN CIRSTOIU
Drywall Nailing 11/15/2021 Partial Approval SORIN CIRSTOIU
Final 2/8/2022 Partial Inspection SORIN CIRSTOIU
SGSOV-Seismic Gas S/O Valve 2/8/2022 SGSOV Not Ready SORIN CIRSTOIU
Smoke Detectors 2/8/2022 Approved SORIN CIRSTOIU
Drywall Nailing 2/10/2022 No Access for Inspection SORIN CIRSTOIU
Wood Frame 2/10/2022 Not Ready for Inspection SORIN CIRSTOIU
Final 3/3/2022 Not Ready for Inspection JONATHAN QUACH
SGSOV-Seismic Gas S/O Valve 3/3/2022 SGSOV Approved JONATHAN QUACH
Final 3/7/2022 Conditional Approval SORIN CIRSTOIU