2523 W KERWIN PL 90065
Certificate Information: 2523 W KERWIN PL 90065
- Application / Permit
- 21016-10000-16003
- Plan Check / Job No.
- B21LA11621
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New roof deck above (E) garage attached to (E) 1-story SFD and new spiral stairs per LA City Standard Plan (#111).
- Permit Issued
- Issued on 4/14/2022
- Issuing Office
- Current Status
- Permit Finaled on 8/27/2022
Permit Application Status History
| Submitted | 6/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2021 | RODOLFO ARIAS |
| Corrections Issued | 7/26/2021 | RODOLFO ARIAS |
| Quality Review Completed | 8/2/2021 | EUGENE BARBEAU |
| Applicant returned to address corrections | 9/17/2021 | RODOLFO ARIAS |
| Applicant returned to address corrections | 12/13/2021 | RODOLFO ARIAS |
| Plan Check Approved | 1/6/2022 | RODOLFO ARIAS |
| Issued | 4/14/2022 | APPLICANT |
| Building Plans Picked Up | 4/21/2022 | APPLICANT |
| Permit Finaled | 8/26/2022 | CRAIG VAUGHAN |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/1/2021 | PATRICK MISCHLICH |
| Eng Process Fee Ord 176,300 | Cleared | 11/23/2021 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 11/23/2021 | CINDY QI |
Contact Information
| Contractor | Os Remodeling Inc; Lic. No.: 1036435-B | 220 N AVENUE 53 #202 LOS ANGELES, CA 90042 |
| Engineer | Chaaya,, Danny Camille; Lic. No.: C45555 | P O BOX 46341 LOS ANGELES, CA 90046 |
| Engineer | Farish,, William Crawford; Lic. No.: C30123 | 19432 CASTLEWOOD CR HUNTINGTON BEACH, CA 92648 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/10/2022 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2022 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| Deck | 7/7/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 7/13/2022 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 7/15/2022 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 7/15/2022 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 7/29/2022 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 7/29/2022 | Approved | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 8/5/2022 | Approved | CRAIG VAUGHAN |
| Final | 8/18/2022 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 8/18/2022 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 8/18/2022 | Approved | CRAIG VAUGHAN |
| Final | 8/24/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 8/26/2022 | Permit Finaled | CRAIG VAUGHAN |