1051 S RIMPAU BLVD 90019
Certificate Information: 1051 S RIMPAU BLVD 90019
- Application / Permit
- 21016-10000-15942
- Plan Check / Job No.
- B21LA11568
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- iNTERIOR AND CONVERT (E) DUPLEX INTO ONE STORY SFD WITH (4) BEDROOM, (3) BATH, (1) LAUNDRY ROOM AND (1) BONUS ROOM.
- Permit Issued
- Issued on 8/12/2021
- Issuing Office
- Current Status
- CofO Issued on 3/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/21/2021 | TSE MING HUANG |
| Corrections Issued | 8/5/2021 | TSE MING HUANG |
| Plan Check Approved | 8/11/2021 | JOSEPH RAFOLS |
| Issued | 8/12/2021 | APPLICANT |
| Building Plans Picked Up | 8/13/2021 | APPLICANT |
| CofO in Progress | 3/7/2022 | ARTHUR SARGSYAN |
| Permit Finaled | 3/2/2023 | DANIEL ORRANTE |
| CofO Issued | 3/2/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/2/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 7/6/2021 | RENZ SORIANO |
| CPC | Cleared | 7/7/2021 | DANIEL CORONADO |
Contact Information
| Contractor | Rebuilt; Lic. No.: 1063540-B | 2201 N LAKEWOOD BLVD STE D643 LONG BEACH, CA 90815 |
| Engineer | Gonzalez,, Felix Bolivar; Lic. No.: C64738 | 14619 CATALINA AVE GARDENA, CA 90247 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/23/2021 | Approved | ARTHUR SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 9/10/2021 | Approved | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 9/10/2021 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 9/17/2021 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 9/17/2021 | Approved | ARTHUR SARGSYAN |
| HVAC-Rough | 9/17/2021 | Approved | ARTHUR SARGSYAN |
| METHANE-Rough | 9/17/2021 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 9/17/2021 | Approved | ARTHUR SARGSYAN |
| Wood Frame | 9/17/2021 | Approved | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 9/22/2021 | Approved | CHRIS CHRISTENSEN |
| Insulation | 9/29/2021 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 10/19/2021 | Approved | ARTHUR SARGSYAN |
| Shower Pan | 10/29/2021 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 12/8/2021 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Final | 2/15/2022 | Approved | ARTHUR SARGSYAN |
| Final | 2/15/2022 | Not Ready for Inspection | ARTHUR SARGSYAN |
| HVAC-Final | 2/15/2022 | Corrections Issued | ARTHUR SARGSYAN |
| PLUMBING-Final | 2/15/2022 | Approved | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 2/15/2022 | SGSOV Approved | ARTHUR SARGSYAN |
| Service/Power Release | 2/15/2022 | Approved | ARTHUR SARGSYAN |
| Smoke Detectors | 2/15/2022 | Not Ready for Inspection | ARTHUR SARGSYAN |
| ELECTRICAL-Final | 3/1/2022 | Approved | ARTHUR SARGSYAN |
| Final | 3/1/2022 | OK to Issue CofO | ARTHUR SARGSYAN |
| HVAC-Final | 3/1/2022 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Final | 3/1/2022 | Approved | ARTHUR SARGSYAN |
| Smoke Detectors | 3/1/2022 | Approved | ARTHUR SARGSYAN |