8461 W MELROSE PL 90069
Certificate Information: 8461 W MELROSE PL 90069
- Application / Permit
- 21016-10000-15801
- Plan Check / Job No.
- B21LA11493
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Beauty Shop or Parlor
- Work Description
- Exterior/Interior tenant improvement of the first & second floors and change of use from office & retail to beauty salon. The scope of work includes new lift to provide accessible path to part of second floor and structural works.
- Permit Issued
- Issued on 11/1/2021
- Issuing Office
- Current Status
- CofO Issued on 9/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2021 | KESETE HAREGOT |
| Corrections Issued | 7/12/2021 | KESETE HAREGOT |
| Disabled Access Plans Picked Up | 7/16/2021 | APPLICANT |
| Quality Review Completed | 7/22/2021 | ALLEN MANALANSAN |
| Plan Check Approved | 10/29/2021 | KESETE HAREGOT |
| Issued | 11/1/2021 | APPLICANT |
| Building Plans Picked Up | 11/1/2021 | APPLICANT |
| TCO Issued (Expire Date: 01-18-2023) | 7/22/2022 | TED RIES |
| CofO in Progress | 8/30/2022 | EDWIN GREGORYONA |
| Permit Finaled | 9/12/2022 | ERNESTO CORRAL |
| CofO Issued | 9/12/2022 | ERNESTO CORRAL |
| Permit Finaled | 9/12/2022 | ERNESTO CORRAL |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/24/2021 | JEANIE LAM |
| Sewer availability | Cleared | 8/25/2021 | JEANIE LAM |
| Green Code | Cleared | 9/14/2021 | KESETE HAREGOT |
| DAS Clearance | Cleared | 9/27/2021 | KESETE HAREGOT |
Contact Information
| Architect | Calnon,, Robert Andrew; Lic. No.: C26387 | 8840 WARNER AVE #100A FOUNTAIN VALLEY, CA 92708 |
| Contractor | Itx Construction/Consultants Inc; Lic. No.: 621867-B | 1285 S LEWIS STREET ANAHEIM, CA 92805 |
| Engineer | Black,, Ian Robert; Lic. No.: S5505 | 19401 OLANA LN HUNTINGTON BEACH, CA 92646 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/21/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 2/9/2022 | Conditional Approval | KATY RAMIREZ |
| Footing/Foundation/Slab | 2/11/2022 | Partial Inspection | KATY RAMIREZ |
| Interior/Exterior Lathing | 3/1/2022 | Partial Approval | EDWIN GREGORYONA |
| Deputy Drilled-In Anchors | 3/10/2022 | Conditional Approval | KATY RAMIREZ |
| Deputy Reinf. Concrete | 3/10/2022 | Conditional Approval | KATY RAMIREZ |
| Green Building Rough | 3/14/2022 | Approved | KATY RAMIREZ |
| Structural Steel Frame | 3/14/2022 | Partial Inspection | KATY RAMIREZ |
| Wood Frame | 3/14/2022 | Partial Approval | KATY RAMIREZ |
| Deputy Drilled-In Anchors | 3/22/2022 | Conditional Approval | TIMOTHY BUXTON |
| Drywall Nailing | 3/22/2022 | Partial Approval | JONATHAN QUACH |
| Insulation | 3/22/2022 | Partial Approval | JONATHAN QUACH |
| Footing/Foundation/Slab | 3/23/2022 | Partial Approval | EDWIN GREGORYONA |
| Light Gage Steel Frame | 4/13/2022 | Partial Inspection | KATY RAMIREZ |
| Drywall Nailing | 5/19/2022 | Approved | KATY RAMIREZ |
| Insulation | 5/19/2022 | Approved | KATY RAMIREZ |
| T-Bar Ceiling | 6/13/2022 | Partial Inspection | KATY RAMIREZ |
| T-Bar Ceiling | 6/21/2022 | Partial Inspection | EDWIN GREGORYONA |
| SGSOV-Seismic Gas S/O Valve | 6/23/2022 | SGSOV Not Ready | BRUCE CAMPBELL |
| T-Bar Ceiling | 6/24/2022 | Partial Inspection | EDWIN GREGORYONA |
| Final | 7/8/2022 | Partial Inspection | EDWIN GREGORYONA |
| Green Building Final | 7/8/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| SGSOV-Seismic Gas S/O Valve | 7/8/2022 | SGSOV Not Ready | EDWIN GREGORYONA |
| Smoke Detectors | 7/8/2022 | Approved | EDWIN GREGORYONA |
| Wood Frame | 7/8/2022 | Approved | EDWIN GREGORYONA |
| Final | 7/12/2022 | Partial Inspection | EDWIN GREGORYONA |
| Green Building Final | 7/12/2022 | Partial Inspection | EDWIN GREGORYONA |
| SGSOV-Seismic Gas S/O Valve | 7/12/2022 | SGSOV Not Ready | EDWIN GREGORYONA |
| Final | 7/20/2022 | OK for TCO | EDWIN GREGORYONA |
| Green Building Final | 7/20/2022 | Approved | EDWIN GREGORYONA |
| SGSOV-Seismic Gas S/O Valve | 7/20/2022 | SGSOV Approved | EDWIN GREGORYONA |
| Special/Order Compliance | 7/20/2022 | Approved | EDWIN GREGORYONA |