1004 W 65TH ST 1-22 90044

Certificate Information: 1004 W 65TH ST 1-22 90044

Application / Permit
21016-10000-15784
Plan Check / Job No.
B21LA11484
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING RECREATION ROOMS AT LEVEL 1 OF EXISTING 20 UNIT APARTMENT BUILDING TO 2 ADUS PER GCS 65852.2 (E)(1)(C)
Permit Issued
Issued on 3/2/2022
Issuing Office
Current Status
CofO Issued on 11/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/17/2021 APPLICANT
Assigned to Plan Check Engineer 6/25/2021 LUKE GONZALES
Corrections Issued 6/28/2021 LUKE GONZALES
Applicant returned to address corrections 11/10/2021 TSE MING HUANG
Applicant returned to address corrections 1/4/2022 RACHEL BEYENE
Plan Check Approved 1/20/2022 RAHEL BEYENE
Plan Check Approved 1/27/2022 RAHEL BEYENE
Building Plans Picked Up 2/1/2022 APPLICANT
Issued 3/2/2022 APPLICANT
CofO in Progress 10/24/2022 RUSSELL BONVOULOIR
CofO Issued 11/1/2022 WINSTON DUNNING
Permit Finaled 11/1/2022 WINSTON DUNNING

Permit Application Clearance Information

Address approval Cleared 7/7/2021 STEVE MELGAR
Sewer availability Cleared 7/7/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 7/9/2021 STEVE MELGAR
Historic Resource Verification Cleared 8/19/2021 MICAELA TORRES-GIL
Hydrant and Access approval Cleared 9/11/2021 JOHN CONNEALLY
Community Plan Implem. Overlay Cleared 9/20/2021 RAFAEL FONTES
Redevelopment Project Area Cleared 10/5/2021 DAVID URITA
Tenant Habitability Plan Cleared 1/20/2022 JORGE ALCANTAR

Contact Information

Contractor Rent Ready Construction Inc; Lic. No.: 1065376-B 631 N SIERRA BONITA AVE      LOS ANGELES, CA 90036

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 3/22/2022 Conditional Approval RUSSELL BONVOULOIR
Insulation 4/6/2022 Approved RUSSELL BONVOULOIR
Drywall Nailing 4/13/2022 Approved RUSSELL BONVOULOIR
Interior/Exterior Lathing 4/13/2022 Not Ready for Inspection RUSSELL BONVOULOIR
Interior/Exterior Lathing 4/14/2022 Approved RUSSELL BONVOULOIR
Final 8/24/2022 Conditional Approval RUSSELL BONVOULOIR
SGSOV-Seismic Gas S/O Valve 8/24/2022 SGSOV Approved RUSSELL BONVOULOIR
Smoke Detectors 8/24/2022 Approved RUSSELL BONVOULOIR