30 E DRIFTWOOD ST 90292
Certificate Information: 30 E DRIFTWOOD ST 90292
- Application / Permit
- 21016-10000-15684
- Plan Check / Job No.
- B21LA11383
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (35) Condo-Multi Family
- Work Description
- Eplan : Soft-Story seismic retrofit per LABC Chapter 93: SOFT STORY SEISMIC REINFORCEMENT AT BUILDING PARKING GARAGE USING WOOD SHEAR WALLS.
- Permit Issued
- Issued on 12/22/2021
- Issuing Office
- Current Status
- CofC Issued on 4/27/2022
Permit Application Status History
| Submitted | 6/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2021 | HANS SANTIAGO |
| Corrections Issued | 7/26/2021 | HANS SANTIAGO |
| Quality Review Completed | 7/28/2021 | SAI KHUM |
| Applicant returned to address corrections | 8/24/2021 | HANS SANTIAGO |
| Plan Check Approved | 12/15/2021 | ANDREW SANTIAGO |
| Issued | 12/22/2021 | APPLICANT |
| OK for CofC | 4/15/2022 | JOHN DODGE |
| CofC Issued | 4/27/2022 | DAVID TSAU |
Permit Application Clearance Information
| Construction near power lines | Cleared | 12/11/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 12/11/2021 | RIDWAN HARDY |
| Tenant Habitability Plan | Cleared | 12/22/2021 | MICHAEL SOTO |
Contact Information
| Contractor | Repipe 1 Restoration Inc; Lic. No.: 1003868-B | , |
| Engineer | Ni,, Zhang Yuan; Lic. No.: NA68149 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/25/2022 | Corrections Issued | GRANT WOODS |
| Deputy Drilled-In Anchors | 2/8/2022 | Conditional Approval | GRANT WOODS |
| Deputy Steel/Welding | 2/8/2022 | Conditional Approval | GRANT WOODS |
| Deputy Drilled-In Anchors | 3/1/2022 | Approved | GRANT WOODS |
| Footing/Foundation/Slab | 3/1/2022 | Partial Approval | GRANT WOODS |
| Wood Frame | 3/1/2022 | Partial Approval | GRANT WOODS |
| Deputy Drilled-In Anchors | 3/15/2022 | Conditional Approval | GRANT WOODS |
| Footing/Foundation/Slab | 3/16/2022 | Approved | GRANT WOODS |
| Wood Frame | 3/16/2022 | Partial Approval | GRANT WOODS |
| Deputy Drilled-In Anchors | 3/21/2022 | Conditional Approval | GRANT WOODS |
| Footing/Foundation/Slab | 3/22/2022 | Approved | GRANT WOODS |
| Wood Frame | 3/22/2022 | Partial Approval | GRANT WOODS |
| Deputy Wood Construction | 3/24/2022 | Conditional Approval | GRANT WOODS |
| Deputy Steel/Welding | 3/29/2022 | Conditional Approval | GRANT WOODS |
| Structural Steel Frame | 4/1/2022 | Approved | JOHN DODGE |
| Wood Frame | 4/1/2022 | Approved | JOHN DODGE |
| Interior/Exterior Lathing | 4/7/2022 | Approved | JOHN DODGE |
| Final | 4/15/2022 | OK for CofC | JOHN DODGE |
| METHANE-Final | 4/15/2022 | Approved | JOHN DODGE |
| SGSOV-Seismic Gas S/O Valve | 4/15/2022 | SGSOV Approved | JOHN DODGE |
| Smoke Detectors | 4/15/2022 | Approved | JOHN DODGE |