8532 W SATURN ST 90035

Certificate Information: 8532 W SATURN ST 90035

Application / Permit
21016-10000-15683
Plan Check / Job No.
B21LA11382
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Soft-Story seismic retrofit per LABC Chapter 93: Install (1) ONE SPECIAL CANTILEVER COLUMN
Permit Issued
Issued on 11/1/2021
Issuing Office
Current Status
CofC Issued on 3/21/2023

Permit Application Status History

Submitted 6/16/2021 APPLICANT
Assigned to Plan Check Engineer 7/21/2021 BIDYUT RATH
Corrections Issued 7/27/2021 BIDYUT RATH
Quality Review Completed 8/3/2021 HANS SANTIAGO
Applicant returned to address corrections 8/26/2021 BIDYUT RATH
Applicant returned to address corrections 8/30/2021 BIDYUT RATH
Applicant returned to address corrections 8/31/2021 BIDYUT RATH
Plan Check Approved 9/9/2021 BIDYUT RATH
Issued 11/1/2021 APPLICANT
OK for CofC 3/30/2022 DARRYL ARNOLD
CofC Issued 3/21/2023 WINSTON DUNNING

Permit Application Clearance Information

Tenant Habitability Plan Cleared 10/28/2021 MICHAEL SOTO

Contact Information

Contractor Zebra Construction Inc; Lic. No.: 1055609-B 145 S FAIRFAX STE 200/300      LOS ANGELES, CA 90036
Engineer Ni,, Zhang Yuan; Lic. No.: C68149 743 S SIERRA VISTA AVE C      ALHAMBRA, CA 91801

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/18/2021 Conditional Approval DARRYL ARNOLD
Excavation/Setback/Form/Re-Bar 12/8/2021 Conditional Approval DARRYL ARNOLD
Footing/Foundation/Slab 12/8/2021 Conditional Approval DARRYL ARNOLD
Structural Steel Frame 12/8/2021 Conditional Approval DARRYL ARNOLD
Wood Frame 12/8/2021 Conditional Approval DARRYL ARNOLD
Interior/Exterior Lathing 12/16/2021 Approved BRUCE CAMPBELL
Final 1/14/2022 Not Ready for Inspection DARRYL ARNOLD
METHANE-Final 1/14/2022 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 1/14/2022 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 1/14/2022 Not Ready for Inspection DARRYL ARNOLD
Final 1/25/2022 Not Ready for Inspection DARRYL ARNOLD
METHANE-Final 1/25/2022 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 1/25/2022 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 1/25/2022 No Access for Inspection DARRYL ARNOLD
Final 2/2/2022 Not Ready for Inspection DARRYL ARNOLD
METHANE-Final 2/2/2022 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 2/2/2022 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 2/2/2022 Not Ready for Inspection DARRYL ARNOLD
Final 3/2/2022 Not Ready for Inspection DARRYL ARNOLD
METHANE-Final 3/2/2022 Conditional Approval DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 3/2/2022 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 3/2/2022 Conditional Approval DARRYL ARNOLD
Final 3/24/2022 Not Ready for Inspection DARRYL ARNOLD
METHANE-Final 3/24/2022 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 3/24/2022 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 3/24/2022 Conditional Approval DARRYL ARNOLD
Final 3/30/2022 OK for CofC DARRYL ARNOLD
METHANE-Final 3/30/2022 Approved DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 3/30/2022 SGSOV Approved DARRYL ARNOLD
Smoke Detectors 3/30/2022 Approved DARRYL ARNOLD