2622 W JEFFERSON BLVD 90018

Certificate Information: 2622 W JEFFERSON BLVD 90018

Application / Permit
21016-10000-15629
Plan Check / Job No.
B21LA11352
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant - Take Out
Work Description
REMODEL OF AN EXISTING PAPI TACOS & CHURROS RESTAURANT "DUE TO FIRE DAMAGE" & KITCHEN EXPANSION TO THE EXISTING LAUNDRY MAT NEXT DOOR. COMBINE THE TWO UNITS INTO ONE
Permit Issued
Issued on 12/16/2022
Issuing Office
Metro
Current Status
CofO Issued on 9/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/17/2021 APPLICANT
Assigned to Plan Check Engineer 7/8/2021 ARSALAN SHABESTARI
Corrections Issued 7/15/2021 ARSALAN SHABESTARI
Building Plans Picked Up 7/26/2021 APPLICANT
Quality Review Completed 8/2/2021 MICHAEL PEREZ
Disabled Access Plans Picked Up 2/8/2022 APPLICANT
Plan Check Approved 9/9/2022 ARSALAN SHABESTARI
Issued 12/16/2022 APPLICANT
CofO in Progress 9/29/2025 ALFREDO LOPEZ
Permit Finaled 9/29/2025 ERNESTO CORRAL
CofO Issued 9/29/2025 ERNESTO CORRAL
Permit Finaled 9/29/2025 ERNESTO CORRAL

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 9/1/2021 KYLE WINSTON
Eng Process Fee Ord 176,300 Cleared 9/1/2021 WALLIE JONG
HPOZ Cleared 9/1/2021 MAX LODER
Sewer availability Cleared 9/7/2021 WALLIE JONG
Historic Resource Verification Cleared 9/16/2021 MICAELA TORRES-GIL
Redevelopment Project Area Cleared 9/16/2021 DAVID URITA
Food Service Establishment Cleared 12/22/2021 JASH PATEL
DAS Clearance Cleared 1/31/2022 ARSALAN SHABESTARI
Food establishment approval Cleared 9/9/2022 LACDHS APPROVED

Contact Information

Contractor Kirmiz Building Inc; Lic. No.: 1026416-B 5208 E GATEWOOD LANE      ANAHEIM, CA 92807

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 1/31/2023 Partial Inspection ALAN MORELOS
Light Gage Steel Frame 2/1/2023 No Access for Inspection MARTIN TAVITIAN
Pre-Inspection 2/13/2023 Not Ready for Inspection MARTIN TAVITIAN
Special/Order Compliance 2/21/2023 Partial Inspection MARTIN TAVITIAN
Light Gage Steel Frame 3/13/2023 Approved MARTIN TAVITIAN
Insulation 3/17/2023 Approved MARTIN TAVITIAN
Drywall Nailing 3/22/2023 Approved ALAN MORELOS
Partition/T-Bar Ceiling 3/29/2023 Partial Inspection MARTIN TAVITIAN
Partition/T-Bar Ceiling 4/21/2023 Not Ready for Inspection VAHE KELEDJIAN
SGSOV-Seismic Gas S/O Valve 5/20/2025 SGSOV Not Ready ALFREDO LOPEZ
Final 9/9/2025 OK to Issue CofO ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 9/9/2025 SGSOV Approved ALFREDO LOPEZ
Smoke Detectors 9/9/2025 Approved ALFREDO LOPEZ
Wood Frame 9/9/2025 Approved ALFREDO LOPEZ