700 N SPAULDING AVE 90046

Certificate Information: 700 N SPAULDING AVE 90046

Application / Permit
21016-10000-15513
Plan Check / Job No.
B21LA11273
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
INITIAL TI IN EXISTING MIXED USE SHELL BUILDING FOR A SALES ROOM SPACE AND ASSOCIATED RESTROOMS, STORAGE AND SERVER ROOM
Permit Issued
Issued on 9/3/2021
Issuing Office
Current Status
Permit Finaled on 1/21/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2021 APPLICANT
Assigned to Plan Check Engineer 7/8/2021 SERGIO GUTIERREZ
Corrections Issued 7/12/2021 SERGIO GUTIERREZ
Quality Review Completed 7/19/2021 ALLEN MANALANSAN
Green Plans Picked Up 7/21/2021 APPLICANT
Disabled Access Plans Picked Up 7/22/2021 APPLICANT
Applicant returned to address corrections 8/3/2021 SERGIO GUTIERREZ
Plan Check Approved 8/26/2021 SERGIO GUTIERREZ
Issued 9/3/2021 APPLICANT
Building Plans Picked Up 9/3/2021 APPLICANT
Permit Finaled 1/21/2022 JONATHAN QUACH

Permit Application Clearance Information

Miscellaneous Cleared 7/26/2021 TERRI OSBORNE
Miscellaneous Cleared 7/26/2021 TERRI OSBORNE
Miscellaneous Cleared 7/26/2021 TERRI OSBORNE
ZA Case Cleared 7/26/2021 TERRI OSBORNE
ZA Case Cleared 7/26/2021 TERRI OSBORNE
ZA Case Cleared 7/26/2021 TERRI OSBORNE
ZA Case Cleared 7/26/2021 TERRI OSBORNE
Fire Marshal Fire Life Safety Cleared 8/3/2021 VIDAL GARCIA
Green Code Cleared 8/5/2021 AARON COSTA
DAS Clearance Cleared 8/19/2021 SERGIO GUTIERREZ

Contact Information

Architect Lahmon,, Mark Karl; Lic. No.: C30068 3834 WILLAT AVENUE      CULVER CITY, CA 90278
Contractor Wilshire Construction L P; Lic. No.: 1048091-B 3470 WILSHIRE STE 1010      LOS ANGELES, CA 90010
Engineer Schroeder,, Mark Ernest; Lic. No.: S4110 16969 VON KARMAN AVE 240      IRVINE, CA 92606

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/29/2021 Partial Approval JONATHAN QUACH
Insulation 9/30/2021 Approved JONATHAN QUACH
Light Gage Steel Frame 9/30/2021 Partial Approval JONATHAN QUACH
Drywall Nailing 10/4/2021 Partial Approval JONATHAN QUACH
Drywall Nailing 10/6/2021 Partial Approval RUSSELL BONVOULOIR
T-Bar Ceiling 11/3/2021 Not Ready for Inspection JONATHAN QUACH
Pre-Inspection 11/4/2021 Approved JONATHAN QUACH
Final 12/9/2021 Conditional Approval JONATHAN QUACH
Green Building Final 12/9/2021 Approved JONATHAN QUACH
Green Building Rough 12/9/2021 Approved JONATHAN QUACH
METHANE-Final 12/9/2021 Approved JONATHAN QUACH
METHANE-Rough 12/9/2021 Approved JONATHAN QUACH
SGSOV-Seismic Gas S/O Valve 12/9/2021 SGSOV Approved JONATHAN QUACH
Smoke Detectors 12/9/2021 Approved JONATHAN QUACH
Wood Frame 12/9/2021 Approved JONATHAN QUACH
Final 12/28/2021 Partial Approval JONATHAN QUACH
Final 1/6/2022 Conditional Approval JONATHAN QUACH