3655 W 5TH ST 90013

Certificate Information: 3655 W 5TH ST 90013

Application / Permit
21016-10000-15504
Plan Check / Job No.
B21LA11267
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING STORAGE TO ADU PER LAMC 12.22 A.33 (c)-(d) ABOVE EXISTING 4 CAR GARAGE.
Permit Issued
Issued on 3/30/2023
Issuing Office
Metro
Current Status
CofO Issued on 8/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2021 APPLICANT
Green Plans Picked Up 6/28/2021 APPLICANT
Assigned to Plan Check Engineer 7/8/2021 SERGIO GUTIERREZ
Corrections Issued 7/12/2021 SERGIO GUTIERREZ
Quality Review Completed 7/16/2021 ALLEN MANALANSAN
Applicant returned to address corrections 4/19/2022 SERGIO GUTIERREZ
Building Plans Picked Up 6/17/2022 APPLICANT
Plan Check Approved 2/16/2023 SERGIO GUTIERREZ
Issued 3/30/2023 APPLICANT
CofO in Progress 8/14/2024 TIMOTHY POWELL
Permit Finaled 8/15/2024 RAFAEL ESPINOZA
CofO Issued 8/15/2024 RAFAEL ESPINOZA
Permit Finaled 8/15/2024 RAFAEL ESPINOZA

Permit Application Clearance Information

Address approval Cleared 1/31/2022 AMAAN MALIK
Sewer availability Cleared 1/31/2022 AMAAN MALIK
ZA Case Cleared 2/3/2022 MAXFIELD VERMY
Eng Process Fee Ord 176,300 Cleared 3/24/2022 CELINA MORENO
Green Code Cleared 2/16/2023 AARON COSTA

Contact Information

Contractor Arreola'S Structural Steel; Lic. No.: 1028192-B 1306 S ATLANTIC DR APT #11      COMPTON, CA 90221

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/12/2023 Partial Inspection KATY RAMIREZ
Green Building Rough 10/4/2023 Approved RONALD JIMENEZ
METHANE-Rough 10/4/2023 Approved RONALD JIMENEZ
Pre-Inspection 10/4/2023 Approved RONALD JIMENEZ
Wood Frame 10/4/2023 Approved RONALD JIMENEZ
Insulation 3/12/2024 Not Ready for Inspection JEROME BLACKWOOD
Insulation 4/26/2024 Partial Approval TIMOTHY POWELL
Insulation 5/1/2024 Approved TIMOTHY POWELL
Drywall Nailing 5/10/2024 Partial Approval RAFAEL CORTES
Drywall Nailing 5/14/2024 Approved RAMAZANALI ALMASI
Final 5/31/2024 Partial Inspection TIMOTHY POWELL
Green Building Final 5/31/2024 Approved TIMOTHY POWELL
SGSOV-Seismic Gas S/O Valve 5/31/2024 SGSOV Not Ready TIMOTHY POWELL
Smoke Detectors 5/31/2024 Approved TIMOTHY POWELL
Final 8/13/2024 OK to Issue CofO TIMOTHY POWELL
SGSOV-Seismic Gas S/O Valve 8/13/2024 SGSOV Approved TIMOTHY POWELL