2200 E TROJAN WAY 150 90033
Certificate Information: 2200 E TROJAN WAY 150 90033
- Application / Permit
- 21016-10000-15458
- Plan Check / Job No.
- B21LA11209
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- Initial T.I. to existing restaurant
- Permit Issued
- Issued on 11/20/2021
- Issuing Office
- Current Status
- Permit Finaled on 6/1/2022
Permit Application Status History
| Submitted | 6/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2021 | RACHEL BEYENE |
| Corrections Issued | 7/13/2021 | RACHEL BEYENE |
| Applicant returned to address corrections | 9/14/2021 | FERNANDO FLORES |
| Applicant returned to address corrections | 11/4/2021 | SHANGQIN XIE |
| Plan Check Approved | 11/8/2021 | SHANGQIN XIE |
| Building Plans Picked Up | 11/12/2021 | APPLICANT |
| Issued | 11/20/2021 | APPLICANT |
| Permit Finaled | 6/1/2022 | MARK FERRARI |
Permit Application Clearance Information
| "Q" conditions | Cleared | 8/6/2021 | JOE LUCKEY |
| "T" removal | Cleared | 8/6/2021 | JOE LUCKEY |
| ZA Case | Cleared | 8/6/2021 | JOE LUCKEY |
| ZA Case | Cleared | 8/6/2021 | JOE LUCKEY |
| ZA Case | Cleared | 8/6/2021 | JOE LUCKEY |
| DAS Clearance | Cleared | 9/16/2021 | CHOI YAN |
| Green Code | Cleared | 9/16/2021 | NEGAR NEJAD |
| Historic Resource Verification | Cleared | 9/29/2021 | MICAELA TORRES-GIL |
| Eng Process Fee Ord 176,300 | Cleared | 10/18/2021 | WALLIE JONG |
| Sewer availability | Cleared | 10/18/2021 | WALLIE JONG |
| Food Service Establishment | Cleared | 10/22/2021 | RAMESHBHAIR PATEL |
| Redevelopment Project Area | Cleared | 10/28/2021 | DAVID URITA |
| Food establishment approval | Cleared | 11/8/2021 | LACDHS APPROVED |
Contact Information
| Architect | , ; Lic. No.: C31661 | 6819 OLD PEAK LANE CORONA, CA 92880 |
| Contractor | Mitchell General Contractors Inc; Lic. No.: 831334-B | 52 TESLA IRVINE, CA 92618 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 12/22/2021 | Partial Approval | MARK FERRARI |
| Light Gage Steel Frame | 12/22/2021 | Partial Approval | MARK FERRARI |
| Footing/Foundation/Slab | 1/13/2022 | Partial Approval | MARK FERRARI |
| Light Gage Steel Frame | 3/25/2022 | Partial Approval | MARK FERRARI |
| Insulation | 3/29/2022 | Approved | MARK FERRARI |
| Drywall Nailing | 3/30/2022 | Partial Approval | MARK FERRARI |
| Wood Frame | 4/18/2022 | Partial Inspection | SORIN CIRSTOIU |
| Light Gage Steel Frame | 4/20/2022 | Partial Approval | JONATHAN QUACH |
| T-Bar Ceiling | 4/20/2022 | Approved | JONATHAN QUACH |
| Drywall Nailing | 4/22/2022 | Approved | JONATHAN QUACH |
| Final | 5/26/2022 | Partial Inspection | MARK FERRARI |
| Green Building Final | 5/26/2022 | Not Ready for Inspection | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 5/26/2022 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 5/26/2022 | Approved | MARK FERRARI |
| Final | 6/1/2022 | Permit Finaled | MARK FERRARI |
| Green Building Final | 6/1/2022 | Approved | MARK FERRARI |