370 N AVENUE 53 90042
Certificate Information: 370 N AVENUE 53 90042
- Application / Permit
- 21016-10000-15426
- Plan Check / Job No.
- B21LA11179
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- FOUNDATION REPAIR TO INSTALL UNDERPINNING PAD FOOTINGS AS PER ENGINEER DESIGN; NO EXTERIOR WORK
- Permit Issued
- Issued on 9/13/2021
- Issuing Office
- Current Status
- Permit Finaled on 2/1/2022
Permit Application Status History
| Submitted | 6/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/15/2021 | RACHEL BEYENE |
| Corrections Issued | 6/16/2021 | RACHEL BEYENE |
| Applicant returned to address corrections | 7/4/2021 | SINA KHOSRAVI |
| Plan Check Approved | 8/27/2021 | RAHEL BEYENE |
| Issued | 9/13/2021 | APPLICANT |
| Building Plans Picked Up | 9/16/2021 | APPLICANT |
| Permit Finaled | 1/31/2022 | HAMIK HARTOUNIAN |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/24/2021 | BRIAN MILLER |
| HPOZ | Cleared | 7/8/2021 | KATIE DEBIASE |
| Tenant Habitability Plan | Cleared | 8/19/2021 | MICHAEL SOTO |
Contact Information
| Contractor | L C Construction; Lic. No.: 837030-B | 5728 YORK BLVD LOS ANGELES, CA 90042 |
| Engineer | Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 | 2160 PARNELL WY ALTADENA, CA 91001 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/16/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 11/23/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 12/1/2021 | Approved | HAMIK HARTOUNIAN |
| Final | 12/30/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 12/30/2021 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 12/30/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 1/31/2022 | Permit Finaled | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 1/31/2022 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 1/31/2022 | Approved | HAMIK HARTOUNIAN |