1541 N ORIOLE LANE 90069
Certificate Information: 1541 N ORIOLE LANE 90069
- Application / Permit
- 21016-10000-15376
- Plan Check / Job No.
- B21LA11148
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR RENOVATION TO SFD AND ATTACHED DECK
- Permit Issued
- Issued on 10/7/2021
- Issuing Office
- Current Status
- Permit Finaled on 8/15/2023
Permit Application Status History
| Submitted | 6/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/18/2021 | FERNANDO FLORES |
| Corrections Issued | 6/23/2021 | FERNANDO FLORES |
| Applicant returned to address corrections | 7/22/2021 | RACHEL BEYENE |
| Plan Check Approved | 8/21/2021 | FERNANDO FLORES |
| Issued | 10/7/2021 | APPLICANT |
| Building Plans Picked Up | 10/8/2021 | APPLICANT |
| Permit Finaled | 8/15/2023 | RAUL BARAJAS |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Wood R S Construction Inc; Lic. No.: 864120-B | 10866 WASHINGTON BLVD 812 CULVER CITY, CA 90232 |
| Engineer | Garcia,, Ricardo Ray; Lic. No.: C66957 | 27702 QUINCY ST CASTAIC, CA 91384 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/29/2021 | Approved | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 12/17/2021 | Approved | ARTHUR SARGSYAN |
| Deputy Drilled-In Anchors | 12/20/2021 | Conditional Approval | RAUL BARAJAS |
| Deputy Wood Construction | 1/26/2022 | Conditional Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2022 | Partial Approval | RAUL BARAJAS |
| Wood Frame | 2/1/2022 | Partial Inspection | RAUL BARAJAS |
| Wood Frame | 3/7/2022 | Partial Approval | RAUL BARAJAS |
| Interior/Exterior Lathing | 8/22/2022 | Partial Approval | RAUL BARAJAS |
| Smoke Detectors | 8/22/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Wood Frame | 8/22/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Wood Frame | 10/25/2022 | Partial Approval | RAUL BARAJAS |
| Interior/Exterior Lathing | 11/14/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Interior/Exterior Lathing | 11/15/2022 | Approved | RAUL BARAJAS |
| Wood Frame | 11/15/2022 | Approved | RAUL BARAJAS |
| Insulation | 11/18/2022 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 11/18/2022 | Partial Approval | RAUL BARAJAS |
| Drywall Nailing | 11/30/2022 | Approved | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 11/30/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 12/6/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Interior/Exterior Lathing | 12/12/2022 | Approved | RAUL BARAJAS |
| Final | 7/14/2023 | Corrections Issued | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 7/14/2023 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 7/14/2023 | Approved | RAUL BARAJAS |
| Final | 8/1/2023 | Corrections Issued | RAUL BARAJAS |
| T-Bar Ceiling | 8/1/2023 | Corrections Issued | RAUL BARAJAS |
| Verify Rec and Parks Fee Memo | 8/1/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Final | 8/15/2023 | Permit Finaled | RAUL BARAJAS |