4736-4738 S 11TH AVE 90043
Certificate Information: 4736-4738 S 11TH AVE 90043
- Application / Permit
- 21016-10000-15221
- Plan Check / Job No.
- B21LA11004
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- INTERIOR RE-DESIGN WHICH INCLUDES THE REMOVAL OF (E) BEARING WALL ( NON-SHEAR WALL)
- Permit Issued
- Issued on 4/14/2022
- Issuing Office
- Current Status
- Issued on 4/14/2022
Permit Application Status History
| Submitted | 2/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/2/2022 | DANIEL SANJUAN |
| Corrections Issued | 2/2/2022 | DANIEL SANJUAN |
| Applicant returned to address corrections | 2/2/2022 | DANIEL SANJUAN |
| Plan Check Approved | 2/3/2022 | DANIEL SANJUAN |
| No Progress | 2/3/2022 | DANIEL SANJUAN |
| Plan Check Approved | 2/17/2022 | DANIEL SANJUAN |
| Issued | 4/14/2022 | APPLICANT |
| Building Plans Picked Up | 5/3/2022 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tsai,, Willy Y; Lic. No.: C35589 | 1545 RUBIO DR SAN MARINO, CA 91108 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 5/13/2022 | Corrections Issued | ANTHONY EGSON |
| Pre-Inspection | 5/31/2022 | Partial Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 6/8/2022 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 6/8/2022 | Partial Approval | ANTHONY EGSON |
| PLUMBING-Rough | 6/8/2022 | Partial Approval | ANTHONY EGSON |
| Shower Pan | 6/29/2022 | Approved | ANTHONY EGSON |
| Wood Frame | 6/29/2022 | Partial Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 7/19/2022 | Partial Approval | ANTHONY EGSON |
| Insulation | 7/26/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 8/25/2022 | Approved | ANTHONY EGSON |
| Final | 1/5/2023 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 1/5/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 1/5/2023 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 1/5/2023 | SGSOV Not Ready | ANTHONY EGSON |
| Smoke Detectors | 1/5/2023 | Approved | ANTHONY EGSON |