707-709 S CRENSHAW BLVD 90005
Certificate Information: 707-709 S CRENSHAW BLVD 90005
- Application / Permit
- 21016-10000-15068
- Plan Check / Job No.
- B21LA10952
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (5) Apartment Hotel
- Work Description
- INTERIOR NON-STRUCTURAL REMODEL FOR APARTMENT HOTEL. 1. GUESTROOMS 707-3. 709-1, 709-3, 707-4, 709-2, 709-4. REMODEL KITCHEN & CONVERT TO LIGHT HOUSEKEEPING. 2. DWELLING UNIT 709-5 & 709-6. ADD 1 BEDROOM & 1 BATHROOM. RELOCATE/REMODEL KITCHEN.
- Permit Issued
- Issued on 1/7/2022
- Issuing Office
- Current Status
- Permit Finaled on 5/8/2024
Permit Application Status History
| Submitted | 6/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2021 | VU NGUYEN |
| Disabled Access Plans Picked Up | 7/2/2021 | APPLICANT |
| Corrections Issued | 7/8/2021 | VU NGUYEN |
| Quality Review Completed | 7/12/2021 | EUGENE BARBEAU |
| Applicant returned to address corrections | 8/14/2021 | VU NGUYEN |
| Plan Check Approved | 10/19/2021 | VU NGUYEN |
| Issued | 1/7/2022 | APPLICANT |
| Building Plans Picked Up | 1/10/2022 | APPLICANT |
| Permit Finaled | 5/8/2024 | WINSTON DUNNING |
Permit Application Clearance Information
| HPOZ | Cleared | 8/13/2021 | AMANDA KAINER |
| Eng Process Fee Ord 176,300 | Cleared | 8/20/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 8/21/2021 | RENZ SORIANO |
| Specific Plan | Cleared | 9/7/2021 | CHI DANG |
| Tenant Habitability Plan | Cleared | 9/23/2021 | RICHARD BRINSON |
| DAS Clearance | Cleared | 10/7/2021 | VU NGUYEN |
Contact Information
| Architect | , ; Lic. No.: C34017 | 905 N. AVENUE 66 LA, CA 90042 |
| Contractor | L A General Builders; Lic. No.: 1044686-B | 8728 ZELZAH AVENUE NORTHRIDGE, CA 91325 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 2/28/2022 | No Access for Inspection | KATY RAMIREZ |
| Wood Frame | 3/9/2022 | Not Ready for Inspection | KATY RAMIREZ |
| Insulation | 3/11/2022 | Approved | KATY RAMIREZ |
| Wood Frame | 3/11/2022 | Approved | KATY RAMIREZ |
| Drywall Nailing | 3/15/2022 | Approved | KATY RAMIREZ |
| Insulation | 3/15/2022 | Partial Approval | KATY RAMIREZ |
| Drywall Nailing | 3/16/2022 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 3/25/2022 | Partial Approval | TED RIES |
| SGSOV-Seismic Gas S/O Valve | 6/14/2022 | SGSOV Not Ready | KATY RAMIREZ |
| Final | 11/29/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 11/29/2023 | SGSOV Not Ready | ALFREDO LOPEZ |
| Smoke Detectors | 11/29/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Final | 1/10/2024 | Not Ready for Inspection | RICARDO ROBLES |
| SGSOV-Seismic Gas S/O Valve | 1/10/2024 | SGSOV Not Ready | RICARDO ROBLES |
| Smoke Detectors | 1/10/2024 | Not Ready for Inspection | RICARDO ROBLES |
| Final | 2/20/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 2/20/2024 | SGSOV Not Ready | ALFREDO LOPEZ |
| Smoke Detectors | 2/20/2024 | Approved | ALFREDO LOPEZ |
| Final | 5/8/2024 | Permit Finaled | WINSTON DUNNING |