333 S GRAND AVE 90017
Certificate Information: 333 S GRAND AVE 90017
- Application / Permit
- 21016-10000-15020
- Plan Check / Job No.
- B21LA10906
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- ePlan Project will involve replacement of existing chillers with high efficiency plate and frame heat exchangers, to be provided chilled water from the District Energy facility (Bunker Hill). Structurally, there are new equipment pads, anchorages, and pipe supports (floor mounted) to facilitate installation of project equipment and piping.
- Permit Issued
- Issued on 3/29/2022
- Issuing Office
- Current Status
- Issued on 3/29/2022
Permit Application Status History
| Submitted | 8/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/6/2021 | HERNAN ARREOLA |
| Corrections Issued | 9/7/2021 | HERNAN ARREOLA |
| Quality Review Completed | 9/16/2021 | JASON HEALEY |
| Plan Check Approved | 11/6/2021 | HERNAN ARREOLA |
| Issued | 3/29/2022 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Air - Tec; Lic. No.: 420650-C20 | 1606 EAST CARSON ST CARSON, CA 90745 |
| Engineer | Snell,, Kirk Joseph; Lic. No.: NA5406 | , |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/21/2022 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 11/21/2022 | Approved | JOEY BUCHANAN |
| Footing/Foundation/Slab | 11/22/2022 | Approved | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 11/22/2022 | Not Ready for Inspection | JOEY BUCHANAN |
| Deputy Drilled-In Anchors | 12/2/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 12/29/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 1/18/2023 | Conditional Approval | KATY RAMIREZ |
| Deputy Drilled-In Anchors | 3/9/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Drilled-In Anchors | 5/11/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 5/11/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 7/19/2023 | Conditional Approval | KATY RAMIREZ |
| Deputy Drilled-In Anchors | 8/21/2023 | Conditional Approval | VAHE KELEDJIAN |
| Footing/Foundation/Slab | 8/23/2023 | Partial Approval | KATY RAMIREZ |
| Deputy Drilled-In Anchors | 8/24/2023 | Conditional Approval | KATY RAMIREZ |
| Deputy Reinf. Concrete | 8/24/2023 | Conditional Approval | KATY RAMIREZ |