3040 E 12TH ST 90023
Certificate Information: 3040 E 12TH ST 90023
- Application / Permit
- 21016-10000-14972
- Plan Check / Job No.
- B21LA10881
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- NEW INTERIOR PARTITIONS TO SUBDIVIDE (E) WAREHOUSE SPCAE INTO SMALLER WAREHOUSE SPACE AND ENGLARGE THE (E) COMMERCIAL SUITE INTO OFFICE. (NO CHANGE OF USE/PARKING/FLOOR AREA) "COMPLY WITH DEPARTMENT ORDER effective date 01/24/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". CEIS Case Number is 890389.
- Permit Issued
- Issued on 12/24/2021
- Issuing Office
- Current Status
- Permit Finaled on 10/11/2022
Permit Application Status History
| Submitted | 6/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/30/2021 | AUNG SOE |
| Corrections Issued | 7/8/2021 | AUNG SOE |
| Quality Review Completed | 7/8/2021 | EUGENE BARBEAU |
| Applicant returned to address corrections | 9/9/2021 | AUNG SOE |
| Disabled Access Plans Picked Up | 9/24/2021 | APPLICANT |
| Green Plans Picked Up | 10/4/2021 | APPLICANT |
| Applicant returned to address corrections | 10/19/2021 | AUNG SOE |
| Plan Check Approved | 10/20/2021 | AUNG SOE |
| Issued | 12/24/2021 | APPLICANT |
| Building Plans Picked Up | 1/5/2022 | APPLICANT |
| Permit Finaled | 10/11/2022 | MARK FERRARI |
Permit Application Clearance Information
| Redevelopment Project Area | Cleared | 8/10/2021 | GRACIELA ACOSTA |
| Green Code | Cleared | 8/23/2021 | AARON COSTA |
| DAS Clearance | Cleared | 9/23/2021 | AUNG SOE |
Contact Information
| Architect | Pak,, Christopher C; Lic. No.: C25621 | 3530 WILSHIRE BLVD SUITE 615 LOS ANGELES, CA 90010 |
| Contractor | Mac Construction Builders Inc; Lic. No.: 1065329-B | 4100 WILSHIRE BLVD #403 LOS ANGELES, CA 90010 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/22/2022 | Partial Approval | MARK FERRARI |
| Deputy Drilled-In Anchors | 2/23/2022 | Conditional Approval | MARK FERRARI |
| Deputy Reinf. Masonry | 2/28/2022 | Conditional Approval | MARK FERRARI |
| Deputy Reinf. Masonry | 3/1/2022 | Conditional Approval | MARK FERRARI |
| Deputy Reinf. Masonry | 3/2/2022 | Conditional Approval | MARK FERRARI |
| Masonry Wall/Backfill | 3/4/2022 | Corrections Issued | MARK FERRARI |
| Deputy Reinf. Masonry | 3/8/2022 | Conditional Approval | MARK FERRARI |
| Masonry Wall/Backfill | 3/10/2022 | Partial Approval | MARK FERRARI |
| Deputy Reinf. Masonry | 3/11/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Drilled-In Anchors | 3/23/2022 | Conditional Approval | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 3/24/2022 | Approved | MARK FERRARI |
| Deputy Reinf. Concrete | 3/25/2022 | Conditional Approval | MARK FERRARI |
| Light Gage Steel Frame | 4/14/2022 | Conditional Approval | DARRYL ARNOLD |
| Insulation | 4/22/2022 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 4/22/2022 | Approved | DARRYL ARNOLD |
| Drywall Nailing | 5/3/2022 | Approved | MARK FERRARI |
| Final | 8/8/2022 | Corrections Issued | MARK FERRARI |
| Green Building Final | 8/8/2022 | Partial Inspection | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 8/8/2022 | SGSOV Not Ready | MARK FERRARI |
| Smoke Detectors | 8/8/2022 | Approved | MARK FERRARI |
| Final | 9/8/2022 | Not Ready for Inspection | MARK FERRARI |
| Green Building Final | 9/8/2022 | Not Ready for Inspection | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 9/8/2022 | SGSOV Not Ready | MARK FERRARI |
| Final | 9/28/2022 | Conditional Approval | MARK FERRARI |
| Green Building Final | 9/28/2022 | Approved | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 9/28/2022 | SGSOV Approved | MARK FERRARI |
| Final | 10/11/2022 | Permit Finaled | MARK FERRARI |