3828 W SUNSET BLVD 90026

Certificate Information: 3828 W SUNSET BLVD 90026

Application / Permit
21016-10000-14718
Plan Check / Job No.
B21LA10698
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
TENANT IMPROVEMENT, NO CHANGE OF USE. REMOVE AND REPLACE (E) STAIRS.
Permit Issued
Issued on 11/10/2021
Issuing Office
Current Status
Permit Finaled on 12/14/2023

Permit Application Status History

Submitted 6/8/2021 APPLICANT
Assigned to Plan Check Engineer 7/12/2021 ZAW HAN
Green Plans Picked Up 7/13/2021 APPLICANT
Corrections Issued 7/14/2021 ZAW HAN
Quality Review Completed 7/29/2021 WING SUEN
Disabled Access Plans Picked Up 8/5/2021 APPLICANT
Applicant returned to address corrections 8/30/2021 ZAW HAN
Plan Check Approved 8/31/2021 ZAW HAN
Issued 11/10/2021 APPLICANT
Building Plans Picked Up 11/12/2021 APPLICANT
Permit Finaled 12/14/2023 RONALD JIMENEZ

Permit Application Clearance Information

DAS Clearance Cleared 7/28/2021 SHINE LIN
Green Code Cleared 8/3/2021 AARON COSTA
Grading Pre-Inspection Cleared 8/30/2021 BARTON HOLMES

Contact Information

Architect , ; Lic. No.: C38399       ,
Contractor Uhles Construction Inc; Lic. No.: 473748-B P O BOX 80237      BAKERSFIELD, CA 93380
Engineer Chavda,, Alpesh Kishorsinh; Lic. No.: C73666 5133 HILLIARD GREEN DR      HILLIARD, OH 43026

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 11/22/2021 Partial Inspection SORIN CIRSTOIU
Wood Frame 11/22/2021 Partial Inspection SORIN CIRSTOIU
Light Gage Steel Frame 11/24/2021 Partial Approval SORIN CIRSTOIU
Wood Frame 11/24/2021 Partial Approval SORIN CIRSTOIU
Drywall Nailing 12/1/2021 Partial Approval SORIN CIRSTOIU
Insulation 12/1/2021 Partial Approval SORIN CIRSTOIU
Structural Steel Frame 12/1/2021 Partial Approval SORIN CIRSTOIU
T-Bar Ceiling 12/6/2021 Partial Inspection SORIN CIRSTOIU
T-Bar Ceiling 12/8/2021 Partial Approval SORIN CIRSTOIU
Structural Steel Frame 1/14/2022 Partial Inspection SORIN CIRSTOIU
Final 2/3/2022 Not Ready for Inspection JONATHAN QUACH
Green Building Final 2/3/2022 Not Ready for Inspection JONATHAN QUACH
SGSOV-Seismic Gas S/O Valve 2/3/2022 SGSOV Approved JONATHAN QUACH
Smoke Detectors 2/3/2022 Not Ready for Inspection JONATHAN QUACH
Final 2/14/2022 Partial Inspection SORIN CIRSTOIU
Green Building Final 2/14/2022 Partial Inspection SORIN CIRSTOIU
Smoke Detectors 2/14/2022 Approved SORIN CIRSTOIU
Final 10/6/2023 Conditional Approval RONALD JIMENEZ
Green Building Final 10/6/2023 Approved RONALD JIMENEZ
Final 12/14/2023 Permit Finaled RONALD JIMENEZ