5938 N TEXHOMA AVE 91316
Certificate Information: 5938 N TEXHOMA AVE 91316
- Application / Permit
- 21016-10000-14717
- Plan Check / Job No.
- B21LA10697
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DET. GARAGE INTO AN ACCESSORY DWELLING UNIT PER LAMC 12.22 A33 (c)&(d).
- Permit Issued
- Issued on 3/18/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/15/2021 | FERNANDO FLORES |
| Corrections Issued | 6/16/2021 | FERNANDO FLORES |
| Building Plans Picked Up | 6/17/2021 | APPLICANT |
| Applicant returned to address corrections | 8/25/2021 | ZAW HAN |
| Plan Check Approved | 12/8/2023 | ANGELICA MARTINEZ |
| Issued | 3/18/2024 | APPLICANT |
| CofO in Progress | 10/17/2024 | MORRIS JACKSON |
| Permit Finaled | 11/18/2024 | JOHN JANSON |
| CofO Issued | 11/18/2024 | JOHN JANSON |
| Permit Finaled | 11/18/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/13/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 7/13/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/14/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/14/2021 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 10/8/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/21/2024 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 3/21/2024 | Corrections Issued | JON MCHUGH |
| Footing/Foundation/Slab | 4/1/2024 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 4/1/2024 | Not Ready for Inspection | JON MCHUGH |
| Footing/Foundation/Slab | 4/4/2024 | Approved | JON MCHUGH |
| PLUMBING-Rough | 4/4/2024 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2024 | Corrections Issued | JON MCHUGH |
| Gas Test | 5/31/2024 | Approved | MORRIS JACKSON |
| Green Building Rough | 5/31/2024 | Not Ready for Inspection | MORRIS JACKSON |
| HVAC-Rough | 5/31/2024 | Not Ready for Inspection | MORRIS JACKSON |
| PLUMBING-Rough | 5/31/2024 | Corrections Issued | MORRIS JACKSON |
| Sewer | 5/31/2024 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 6/5/2024 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Rough | 6/5/2024 | Corrections Issued | JON MCHUGH |
| Green Building Rough | 6/5/2024 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Rough | 6/5/2024 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 6/5/2024 | Corrections Issued | JON MCHUGH |
| BUILDING-Rough-Frame | 6/20/2024 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Rough | 6/20/2024 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Rough | 6/20/2024 | Not Ready for Inspection | JON MCHUGH |
| Interior/Exterior Lathing | 6/20/2024 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 6/20/2024 | Not Ready for Inspection | JON MCHUGH |
| BUILDING-Rough-Frame | 6/25/2024 | Not Ready for Inspection | MORRIS JACKSON |
| ELECTRICAL-Rough | 6/25/2024 | Partial Approval | MORRIS JACKSON |
| Green Building Rough | 6/25/2024 | Not Ready for Inspection | MORRIS JACKSON |
| HVAC-Rough | 6/25/2024 | Partial Approval | MORRIS JACKSON |
| PLUMBING-Rough | 6/25/2024 | Partial Approval | MORRIS JACKSON |
| Insulation | 6/27/2024 | Approved | JON MCHUGH |
| Drywall Nailing | 7/8/2024 | Not Ready for Inspection | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2024 | Approved | MORRIS JACKSON |
| Shower Pan | 7/8/2024 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 7/11/2024 | Approved | JON MCHUGH |
| Drywall Nailing | 7/11/2024 | Approved | JON MCHUGH |
| Green Building Rough | 7/11/2024 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 7/11/2024 | Approved | JON MCHUGH |
| Final | 9/11/2024 | Corrections Issued | JON MCHUGH |
| Green Building Final | 9/11/2024 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 9/11/2024 | SGSOV Approved | JON MCHUGH |
| Smoke Detectors | 9/11/2024 | Approved | JON MCHUGH |
| Final | 9/16/2024 | Corrections Issued | MORRIS JACKSON |
| Final | 10/17/2024 | OK to Issue CofO | MORRIS JACKSON |
| Service/Power Release | 10/17/2024 | Approved | MORRIS JACKSON |