4561 W COLORADO BLVD 90039

Certificate Information: 4561 W COLORADO BLVD 90039

Application / Permit
21016-10000-14697
Plan Check / Job No.
B21LA10680
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(23) Sound Stage
Work Description
CHANGE OF USE FROM (E) ONE STORAGE BUILDING TO TELEVISION PRODUCTION STUDIO (WITHOUT STUDIO AUDIENCE) INCLUDES NEW ACCOUSTICALLY SEPARATED STAGE ENCLOSURE, NON-LOADBEARING PARTITIONS & CEILINGS & NEW TRUSSES BELOW (E) ROOF, INTERIOR GLAZING, EXTERIOR & INTERIOR DOORS, & NEW RESTROOMS.( no parking change).
Permit Issued
Issued on 11/19/2021
Issuing Office
Current Status
CofO Issued on 1/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2021 APPLICANT
Assigned to Plan Check Engineer 7/8/2021 GARO TELMI
Corrections Issued 7/21/2021 GARO TELMI
Quality Review Completed 7/29/2021 MICHAEL PEREZ
Building Plans Picked Up 7/30/2021 APPLICANT
Applicant returned to address corrections 8/26/2021 GARO TELMI
Green Plans Picked Up 8/26/2021 APPLICANT
Applicant returned to address corrections 10/4/2021 GARO TELMI
Applicant returned to address corrections 10/19/2021 GARO TELMI
Plan Check Approved 11/17/2021 GARO TELMI
Plan Check Approved 11/19/2021 GARO TELMI
Issued 11/19/2021 APPLICANT
CofO in Progress 1/13/2023 ERNESTO CORRAL
CofO Issued 1/13/2023 ERNESTO CORRAL
Permit Finaled 1/13/2023 ERNESTO CORRAL

Permit Application Clearance Information

ZI Cleared 7/28/2021 ANNA VIDAL
Eng Process Fee Ord 176,300 Cleared 8/3/2021 RENZ SORIANO
Sewer availability Cleared 8/11/2021 RENZ SORIANO
Green Code Cleared 8/26/2021 AARON COSTA
Motion picture studio Cleared 10/26/2021 VIDAL GARCIA
DAS Clearance Cleared 11/8/2021 GARO TELMI

Contact Information

Architect 8970, Washington Blvd.; Lic. No.: C35493       CULVER CITY, CA 90232
Contractor Environmental Contracting Corporation; Lic. No.: 491028-B 880 EAST 1ST STREET      LOS ANGELES, CA 90012
Engineer Chang,, Wayne Chia-Wei; Lic. No.: S4751 19210 S VERMONT AVE BLDG B STE 210      GARDENA, CA 90248

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/23/2021 Approved JONATHAN QUACH
Footing/Foundation/Slab 11/23/2021 Approved JONATHAN QUACH
Footing/Foundation/Slab 11/29/2021 Partial Inspection SORIN CIRSTOIU
Deputy Drilled-In Anchors 11/30/2021 Conditional Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 11/30/2021 Conditional Approval SORIN CIRSTOIU
Footing/Foundation/Slab 12/3/2021 Not Ready for Inspection SORIN CIRSTOIU
Deputy Reinf. Concrete 12/7/2021 Conditional Approval SORIN CIRSTOIU
Reinforced Concrete Frame 1/24/2022 Partial Approval BRUCE CAMPBELL
Deputy Reinf. Concrete 1/25/2022 Conditional Approval KATY RAMIREZ
Light Gage Steel Frame 2/1/2022 Partial Approval SORIN CIRSTOIU
Drywall Nailing 2/4/2022 Partial Approval SORIN CIRSTOIU
Drywall Nailing 2/7/2022 Partial Approval SORIN CIRSTOIU
Light Gage Steel Frame 2/7/2022 Partial Approval SORIN CIRSTOIU
Deputy Steel/Welding 2/9/2022 Conditional Approval SORIN CIRSTOIU
Deputy Steel/Welding 2/10/2022 Approved SORIN CIRSTOIU
Drywall Nailing 2/10/2022 Partial Approval SORIN CIRSTOIU
Light Gage Steel Frame 2/10/2022 Partial Approval SORIN CIRSTOIU
Deputy Steel/Welding 2/11/2022 Conditional Approval SORIN CIRSTOIU
Deputy Steel/Welding 2/14/2022 Conditional Approval SORIN CIRSTOIU
Deputy Steel/Welding 2/15/2022 Conditional Approval SORIN CIRSTOIU
Drywall Nailing 2/23/2022 Partial Approval SORIN CIRSTOIU
Light Gage Steel Frame 2/23/2022 Partial Approval SORIN CIRSTOIU
Deputy Steel/Welding 2/25/2022 Conditional Approval SORIN CIRSTOIU
Deputy Steel/Welding 2/28/2022 Conditional Approval SORIN CIRSTOIU
Deputy Steel/Welding 3/1/2022 Partial Approval SORIN CIRSTOIU
Deputy Steel/Welding 3/2/2022 Conditional Approval SORIN CIRSTOIU
Deputy Steel/Welding 3/3/2022 Conditional Approval JONATHAN QUACH
Drywall Nailing 3/7/2022 Partial Approval SORIN CIRSTOIU
Light Gage Steel Frame 3/7/2022 Partial Approval SORIN CIRSTOIU
Drywall Nailing 3/21/2022 Partial Approval SORIN CIRSTOIU
Light Gage Steel Frame 3/21/2022 Partial Approval SORIN CIRSTOIU
Structural Steel Frame 3/21/2022 Partial Approval SORIN CIRSTOIU
Deputy Drilled-In Anchors 3/22/2022 Conditional Approval SORIN CIRSTOIU
Deputy Steel/Welding 3/22/2022 Conditional Approval SORIN CIRSTOIU
Deputy Drilled-In Anchors 3/23/2022 Conditional Approval SORIN CIRSTOIU
Deputy Steel/Welding 3/23/2022 Conditional Approval SORIN CIRSTOIU
Deputy Drilled-In Anchors 3/24/2022 Conditional Approval SORIN CIRSTOIU
Deputy Steel/Welding 3/24/2022 Conditional Approval SORIN CIRSTOIU
Deputy Drilled-In Anchors 3/25/2022 Conditional Approval SORIN CIRSTOIU
Deputy Steel/Welding 3/25/2022 Conditional Approval SORIN CIRSTOIU
Deputy Drilled-In Anchors 3/29/2022 Approved SORIN CIRSTOIU
Deputy Steel/Welding 3/29/2022 Approved SORIN CIRSTOIU
Drywall Nailing 3/29/2022 Partial Approval SORIN CIRSTOIU
Light Gage Steel Frame 3/29/2022 Partial Approval SORIN CIRSTOIU
Drywall Nailing 4/20/2022 Partial Approval SORIN CIRSTOIU
Light Gage Steel Frame 4/20/2022 Partial Approval SORIN CIRSTOIU
Reinforced Concrete Frame 5/4/2022 Partial Approval JONATHAN QUACH
Deputy Reinf. Concrete 5/6/2022 Conditional Approval JONATHAN QUACH
Light Gage Steel Frame 6/2/2022 Approved JONATHAN QUACH
T-Bar Ceiling 6/2/2022 Partial Approval JONATHAN QUACH
Pre-Inspection 6/30/2022 Corrections Issued JONATHAN QUACH
Special/Order Compliance 7/1/2022 Order to Comply Issued JONATHAN QUACH
Final 10/19/2022 Conditional Approval JONATHAN QUACH
Green Building Final 10/19/2022 Approved JONATHAN QUACH
Green Building Rough 10/19/2022 Approved JONATHAN QUACH
SGSOV-Seismic Gas S/O Valve 10/19/2022 SGSOV Approved JONATHAN QUACH
Smoke Detectors 10/19/2022 Approved JONATHAN QUACH
Wood Frame 10/19/2022 Approved JONATHAN QUACH