3206 W WINDSOR AVE 90039
Certificate Information: 3206 W WINDSOR AVE 90039
- Application / Permit
- 21016-10000-14615
- Plan Check / Job No.
- B21LA10623
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior/Exterior remodel to (E) two-story Single Family Dwelling. Scope of work to include remodel of first floor.
- Permit Issued
- Issued on 12/22/2021
- Issuing Office
- Current Status
- Issued on 12/22/2021
Permit Application Status History
| Submitted | 6/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/14/2021 | ADAM HEGAZI |
| Corrections Issued | 6/15/2021 | ADAM HEGAZI |
| Plan Check Approved | 12/22/2021 | CHRISTOPHER KOMANCHECK |
| Issued | 12/22/2021 | APPLICANT |
| Building Plans Picked Up | 1/25/2022 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/6/2021 | ROBERT HUGHES |
Contact Information
| Architect | Keltner,, Shawn J; Lic. No.: C36976 | 3737 AGUILAR ST LOS ANGELES, CA 90065 |
| Contractor | Owner-Builder | , |
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Wood Construction | 3/18/2022 | Conditional Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 3/23/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 3/23/2022 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 5/11/2022 | Approved | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 5/11/2022 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 5/11/2022 | Partial Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 5/18/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 5/18/2022 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 5/18/2022 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 5/18/2022 | Corrections Issued | THOMAS LOGRASSO |
| Deputy Wood Construction | 5/24/2022 | Conditional Approval | RUBEN SALAS |
| BUILDING-Rough-Frame | 5/31/2022 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 5/31/2022 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 6/10/2022 | Approved | THOMAS LOGRASSO |
| Final | 11/10/2022 | Corrections Issued | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 11/10/2022 | SGSOV Approved | THOMAS LOGRASSO |
| Smoke Detectors | 11/10/2022 | Approved | THOMAS LOGRASSO |