1001 S MALCOLM AVE 1-9 90024
Certificate Information: 1001 S MALCOLM AVE 1-9 90024
- Application / Permit
- 21016-10000-14576
- Plan Check / Job No.
- B21LA10597
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT (E) BASEMENT TO (1) NEW ADU ON (E) TWO STORY APARTMENT (5 UNITS) PER GCS 65852.2 (E)(1)(C)
- Permit Issued
- Issued on 6/17/2022
- Issuing Office
- Current Status
- CofO Issued on 9/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2021 | TSE MING HUANG |
| Corrections Issued | 6/10/2021 | TSE MING HUANG |
| Applicant returned to address corrections | 6/11/2021 | TSE MING HUANG |
| Building Plans Picked Up | 6/15/2021 | APPLICANT |
| Applicant returned to address corrections | 9/17/2021 | TSE MING HUANG |
| Plan Check Approved | 5/11/2022 | ADAM HEGAZI |
| Issued | 6/17/2022 | APPLICANT |
| CofO in Progress | 7/16/2024 | MICHAEL PETRUSKO |
| Permit Finaled | 9/4/2024 | DAVID TSAU |
| CofO Issued | 9/4/2024 | DAVID TSAU |
| Permit Finaled | 9/4/2024 | DAVID TSAU |
Permit Application Clearance Information
| "Q" conditions | Cleared | 6/18/2021 | TERRI OSBORNE |
| Specific Plan | Cleared | 6/22/2021 | KEVIN FULTON |
| Specific Plan | Cleared | 6/22/2021 | KEVIN FULTON |
| Address approval | Cleared | 6/23/2021 | DINAH GARIN |
| Sewer availability | Cleared | 6/23/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/25/2021 | DINAH GARIN |
| Specific Plan | Cleared | 7/26/2021 | KEVIN ARUCAN |
| Green Code | Cleared | 8/18/2021 | TSE MING HUANG |
Contact Information
| Contractor | Rent Ready Construction Inc; Lic. No.: 1065376-B | 631 N SIERRA BONITA AVE LOS ANGELES, CA 90036 |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/4/2023 | Partial Inspection | SHAVONNE ESPINOZA |
| Deputy Drilled-In Anchors | 11/27/2023 | Conditional Approval | PAUL DAVIDSON |
| Pre-Inspection | 11/28/2023 | Partial Inspection | CASIMIR BRITTON |
| Footing/Foundation/Slab | 12/1/2023 | Approved | CASIMIR BRITTON |
| Green Building Rough | 1/30/2024 | Approved | PAUL DAVIDSON |
| Interior/Exterior Lathing | 1/30/2024 | Partial Approval | PAUL DAVIDSON |
| Wood Frame | 1/30/2024 | Approved | PAUL DAVIDSON |
| Insulation | 2/2/2024 | Approved | CASIMIR BRITTON |
| Interior/Exterior Lathing | 2/2/2024 | Approved | CASIMIR BRITTON |
| Drywall Nailing | 2/27/2024 | Approved | PAUL DAVIDSON |
| Final | 7/16/2024 | OK to Issue CofO | MICHAEL PETRUSKO |
| Green Building Final | 7/16/2024 | Approved | MICHAEL PETRUSKO |
| SGSOV-Seismic Gas S/O Valve | 7/16/2024 | SGSOV Approved | MICHAEL PETRUSKO |
| Smoke Detectors | 7/16/2024 | Approved | MICHAEL PETRUSKO |