7851 S MCCONNELL AVE 90045
Certificate Information: 7851 S MCCONNELL AVE 90045
- Application / Permit
- 21016-10000-14552
- Plan Check / Job No.
- B21LA10569
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan ADU conversion. Convert existing 2 car garage to ADU per LAMC 12.22A.33(B)5
- Permit Issued
- Issued on 1/11/2022
- Issuing Office
- Current Status
- Issued on 1/11/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/9/2021 | MONICA RAMIREZ |
| Corrections Issued | 6/10/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 7/19/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 9/16/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 9/27/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 10/12/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 11/2/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 11/17/2021 | MONICA RAMIREZ |
| Plan Check Approved | 11/23/2021 | MONICA RAMIREZ |
| Issued | 1/11/2022 | APPLICANT |
Permit Application Clearance Information
| Hold | Cleared | 8/17/2021 | Yasaman Shayesteh |
| Address approval | Cleared | 9/16/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 9/16/2021 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 9/23/2021 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 10/27/2021 | PEDRO AYALA |
| Construction near power lines | Cleared | 11/22/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVENUE LONG BEACH, CA 90813 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/18/2022 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 3/14/2022 | Approved | BOBBY KEY |
| Underground Mechanical | 3/14/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 4/26/2022 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 4/26/2022 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 4/26/2022 | Approved | BOBBY KEY |
| Green Building Rough | 4/26/2022 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Rough | 5/18/2022 | Approved | RICHARD STEINBACH |
| HVAC-Rough | 5/18/2022 | Approved | RICHARD STEINBACH |
| PLUMBING-Rough | 5/18/2022 | Approved | RICHARD STEINBACH |
| Shower Pan | 5/18/2022 | Approved | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 5/25/2022 | Conditional Approval | BOBBY KEY |
| PLUMBING-Rough | 5/25/2022 | Corrections Issued | BOBBY KEY |
| Green Building Rough | 5/31/2022 | Approved | BOBBY KEY |
| Insulation | 5/31/2022 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 5/31/2022 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 5/31/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 6/3/2022 | Approved | BOBBY KEY |
| Drywall Nailing | 6/3/2022 | Approved | BOBBY KEY |
| Final | 6/3/2022 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Final | 7/26/2022 | Approved | BOBBY KEY |
| Final | 7/26/2022 | Corrections Issued | BOBBY KEY |
| Green Building Final | 7/26/2022 | Approved | BOBBY KEY |
| HVAC-Final | 7/26/2022 | Approved | BOBBY KEY |
| PLUMBING-Final | 7/26/2022 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 7/26/2022 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 7/26/2022 | Approved | BOBBY KEY |
| Special/Order Compliance | 2/29/2024 | Corrections Issued | BOBBY KEY |
| Final | 6/26/2024 | Corrections Issued | BOBBY KEY |