450 N MUSEUM DR 90065
Certificate Information: 450 N MUSEUM DR 90065
- Application / Permit
- 21016-10000-14517
- Plan Check / Job No.
- B21LA10540
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- GARAGE CONVERSION TO ADU PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 10/8/2021
- Issuing Office
- Current Status
- CofO Issued on 7/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/7/2021 | SHANGQIN XIE |
| Corrections Issued | 6/7/2021 | SHANGQIN XIE |
| Plan Check Approved | 10/7/2021 | SHANGQIN XIE |
| Issued | 10/8/2021 | APPLICANT |
| Building Plans Picked Up | 10/15/2021 | APPLICANT |
| CofO in Progress | 6/27/2022 | OSVALDO PARAMO |
| CofO in Progress | 6/27/2022 | OSVALDO PARAMO |
| Permit Finaled | 7/9/2022 | DEROLD HAUFF |
| CofO Issued | 7/9/2022 | DEROLD HAUFF |
| Permit Finaled | 7/9/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/16/2021 | CELINA MORENO |
| Sewer availability | Cleared | 6/16/2021 | CELINA MORENO |
| Address approval | Cleared | 6/22/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 6/22/2021 | CELINA MORENO |
| Specific Plan | Cleared | 6/25/2021 | DYLAN LAWRENCE |
| Grading Pre-Inspection | Cleared | 9/9/2021 | PATRICK MISCHLICH |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/22/2021 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 1/26/2022 | Partial Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 2/25/2022 | Partial Approval | OSVALDO PARAMO |
| Rough-Elec/Plmb/HVAC | 2/25/2022 | Corrections Issued | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 3/4/2022 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2022 | Partial Approval | OSVALDO PARAMO |
| Rough-Elec/Plmb/HVAC | 3/4/2022 | Approved | OSVALDO PARAMO |
| Sewer | 3/4/2022 | Approved | OSVALDO PARAMO |
| Insulation | 3/9/2022 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 3/9/2022 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 3/16/2022 | Approved | HAMIK HARTOUNIAN |
| Gas Test | 3/16/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 4/28/2022 | Corrections Issued | OSVALDO PARAMO |
| Gas Test | 4/28/2022 | Approved | OSVALDO PARAMO |
| PLUMBING-Final | 4/28/2022 | Approved | OSVALDO PARAMO |
| Smoke Detectors | 4/28/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 4/29/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Green Building Final | 4/29/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 4/29/2022 | SGSOV Not Ready | OSVALDO PARAMO |
| Final | 5/4/2022 | Conditional Approval | OSVALDO PARAMO |
| Green Building Final | 5/4/2022 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 5/4/2022 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 5/4/2022 | Approved | OSVALDO PARAMO |
| Final | 6/13/2022 | OK to Issue CofO | OSVALDO PARAMO |