450 N MUSEUM DR 90065

Certificate Information: 450 N MUSEUM DR 90065

Application / Permit
21016-10000-14517
Plan Check / Job No.
B21LA10540
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
GARAGE CONVERSION TO ADU PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 10/8/2021
Issuing Office
Current Status
CofO Issued on 7/9/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/5/2021 APPLICANT
Assigned to Plan Check Engineer 6/7/2021 SHANGQIN XIE
Corrections Issued 6/7/2021 SHANGQIN XIE
Plan Check Approved 10/7/2021 SHANGQIN XIE
Issued 10/8/2021 APPLICANT
Building Plans Picked Up 10/15/2021 APPLICANT
CofO in Progress 6/27/2022 OSVALDO PARAMO
CofO in Progress 6/27/2022 OSVALDO PARAMO
Permit Finaled 7/9/2022 DEROLD HAUFF
CofO Issued 7/9/2022 DEROLD HAUFF
Permit Finaled 7/9/2022 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/16/2021 CELINA MORENO
Sewer availability Cleared 6/16/2021 CELINA MORENO
Address approval Cleared 6/22/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 6/22/2021 CELINA MORENO
Specific Plan Cleared 6/25/2021 DYLAN LAWRENCE
Grading Pre-Inspection Cleared 9/9/2021 PATRICK MISCHLICH

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/22/2021 Approved OSVALDO PARAMO
PLUMBING-Rough 1/26/2022 Partial Approval OSVALDO PARAMO
BUILDING-Rough-Frame 2/25/2022 Partial Approval OSVALDO PARAMO
Rough-Elec/Plmb/HVAC 2/25/2022 Corrections Issued OSVALDO PARAMO
BUILDING-Rough-Frame 3/4/2022 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 3/4/2022 Partial Approval OSVALDO PARAMO
Rough-Elec/Plmb/HVAC 3/4/2022 Approved OSVALDO PARAMO
Sewer 3/4/2022 Approved OSVALDO PARAMO
Insulation 3/9/2022 Approved OSVALDO PARAMO
Interior/Exterior Lathing 3/9/2022 Approved OSVALDO PARAMO
Drywall Nailing 3/16/2022 Approved HAMIK HARTOUNIAN
Gas Test 3/16/2022 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Final 4/28/2022 Corrections Issued OSVALDO PARAMO
Gas Test 4/28/2022 Approved OSVALDO PARAMO
PLUMBING-Final 4/28/2022 Approved OSVALDO PARAMO
Smoke Detectors 4/28/2022 Not Ready for Inspection OSVALDO PARAMO
Final 4/29/2022 Not Ready for Inspection OSVALDO PARAMO
Green Building Final 4/29/2022 Not Ready for Inspection OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 4/29/2022 SGSOV Not Ready OSVALDO PARAMO
Final 5/4/2022 Conditional Approval OSVALDO PARAMO
Green Building Final 5/4/2022 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 5/4/2022 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 5/4/2022 Approved OSVALDO PARAMO
Final 6/13/2022 OK to Issue CofO OSVALDO PARAMO