4506 S KANSAS AVE 90037
Certificate Information: 4506 S KANSAS AVE 90037
- Application / Permit
- 21016-10000-14496
- Plan Check / Job No.
- B21LA10521
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- GARAGE CONVERSION TO ACCESSORY DWELLING UNIT. WORK PER ENGINEERED DESIGN.
- Permit Issued
- Issued on 3/6/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2021 | JOSEPH RAFOLS |
| Corrections Issued | 6/9/2021 | JOSEPH RAFOLS |
| Building Plans Picked Up | 6/17/2021 | APPLICANT |
| Plan Check Approved | 9/30/2021 | GEORGE ALVAREZ |
| Issued | 3/6/2023 | APPLICANT |
| CofO in Progress | 11/7/2023 | CRAIG DAVIS |
| CofO Issued | 12/27/2023 | DEROLD HAUFF |
| Permit Finaled | 12/27/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 6/21/2021 | RICARDO BOHORQUEZ |
| Address approval | Cleared | 7/6/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2021 | JEANIE LAM |
| Sewer availability | Cleared | 7/6/2021 | JEANIE LAM |
| ZI | Cleared | 8/10/2021 | GISELLE CORELLA |
| ZI | Cleared | 9/27/2021 | RAFAEL FONTES |
Contact Information
| Contractor | Efren Hernandez Builder Inc; Lic. No.: 1101304-B | 3434 PONTIAC AVE JURUPA VALLEY, CA 92509 |
| Engineer | Rodriguez,, Jacob; Lic. No.: S5084 | 8206 ENCINO AVE NORTHRIDGE, CA 91325 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/10/2023 | Conditional Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 3/13/2023 | Corrections Issued | SABAS ALONSO |
| Sewer | 3/13/2023 | Approved | SABAS ALONSO |
| Underground Mechanical | 3/13/2023 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 3/22/2023 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 3/28/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Insulation | 3/28/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 3/28/2023 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 4/20/2023 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2023 | Approved | SABAS ALONSO |
| Green Building Rough | 4/20/2023 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 4/20/2023 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 4/25/2023 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 4/25/2023 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2023 | Approved | SABAS ALONSO |
| Green Building Rough | 4/25/2023 | Approved | SABAS ALONSO |
| HVAC-Rough | 4/25/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 4/25/2023 | Approved | SABAS ALONSO |
| Shower Pan | 4/25/2023 | Corrections Issued | SABAS ALONSO |
| Insulation | 5/1/2023 | Corrections Issued | BRENDAN MORELLI |
| Drywall Nailing | 5/3/2023 | Approved | SABAS ALONSO |
| Insulation | 5/3/2023 | Approved | SABAS ALONSO |
| Final | 10/3/2023 | Corrections Issued | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 10/3/2023 | SGSOV Not Ready | RONNIE MINDANAO |
| Smoke Detectors | 10/3/2023 | Corrections Issued | RONNIE MINDANAO |
| Final | 10/10/2023 | Corrections Issued | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 10/10/2023 | SGSOV Not Required | RONNIE MINDANAO |
| Smoke Detectors | 10/10/2023 | Approved | RONNIE MINDANAO |
| Final | 10/13/2023 | Not Ready for Inspection | CRAIG DAVIS |
| Final | 10/18/2023 | Conditional Approval | MICHAEL LEWIS |
| Final | 11/6/2023 | OK to Issue CofO | CRAIG DAVIS |
| Service/Power Release | 11/6/2023 | Approved | CRAIG DAVIS |