8475 W MELROSE PL 90069
Certificate Information: 8475 W MELROSE PL 90069
- Application / Permit
- 21016-10000-14429
- Plan Check / Job No.
- B21LA10487
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- TENANT IMPROVEMENT TO EXISTING CAFE.
- Permit Issued
- Issued on 11/16/2021
- Issuing Office
- Current Status
- Issued on 11/16/2021
Permit Application Status History
| Submitted | 6/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2021 | JOE VO |
| Corrections Issued | 6/10/2021 | JOE VO |
| Applicant returned to address corrections | 7/13/2021 | JOE VO |
| Building Plans Picked Up | 10/28/2021 | APPLICANT |
| Plan Check Approved | 11/10/2021 | JOE VO |
| Issued | 11/16/2021 | APPLICANT |
Permit Application Clearance Information
| ZA Case | Cleared | 11/8/2021 | NAOMI GUTH |
| Food establishment approval | Cleared | 11/10/2021 | LACDHS APPROVED |
Contact Information
| Contractor | Beresheet Construction & Design Inc; Lic. No.: 1057051-B | 8362 1/2 WEST 3RD STREET LOS ANGELES, CA 90048 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 3/15/2022 | Partial Approval | KATY RAMIREZ |
| Pre-Inspection | 3/15/2022 | Approved | KATY RAMIREZ |
| Wood Frame | 3/15/2022 | Partial Approval | KATY RAMIREZ |
| Deputy Reinf. Concrete | 4/1/2022 | Conditional Approval | KATY RAMIREZ |
| Footing/Foundation/Slab | 4/13/2022 | Partial Inspection | KATY RAMIREZ |
| Insulation | 4/13/2022 | Conditional Approval | KATY RAMIREZ |
| Light Gage Steel Frame | 4/13/2022 | Approved | KATY RAMIREZ |
| Wood Frame | 4/13/2022 | Partial Inspection | KATY RAMIREZ |
| Drywall Nailing | 5/9/2022 | Approved | KATY RAMIREZ |
| Interior/Exterior Lathing | 5/9/2022 | Approved | KATY RAMIREZ |
| Interior/Exterior Lathing | 7/12/2022 | Approved | EDWIN GREGORYONA |
| Pre-Inspection | 7/12/2022 | Approved | EDWIN GREGORYONA |
| Wood Frame | 7/12/2022 | Approved | EDWIN GREGORYONA |
| Pre-Inspection | 7/28/2022 | Approved | KATY RAMIREZ |
| Pre-Inspection | 8/8/2022 | No Access for Inspection | EDWIN GREGORYONA |
| Final | 10/7/2022 | Not Ready for Inspection | DAVID BURKHEAD |
| SGSOV-Seismic Gas S/O Valve | 10/7/2022 | SGSOV Not Ready | DAVID BURKHEAD |
| Smoke Detectors | 10/7/2022 | Not Ready for Inspection | DAVID BURKHEAD |
| Final | 10/13/2022 | Partial Approval | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 10/13/2022 | SGSOV Approved | TIMOTHY BUXTON |
| Smoke Detectors | 10/13/2022 | Approved | TIMOTHY BUXTON |