1000 W 8TH ST 90017

Certificate Information: 1000 W 8TH ST 90017

Application / Permit
21016-10000-14418
Plan Check / Job No.
B21LA10482
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
TENANT IMPROVEMENT OF TOP TWO RESIDENTIAL FLOORS - L58 & L59 PENTHOUSE UNITS, COMMON SPACES (CORRIDOR, ETC.) NO CHANGE IN USE OR OCCUPANT LOADS TO INCLUDE: NEW NON-LOAD BEARING PARTITIONS,DOORS, CEILINGS, FINISHES POWER, LOW VOLTAGE.
Permit Issued
Issued on 12/1/2021
Issuing Office
Current Status
Permit Finaled on 12/13/2022

Permit Application Status History

Submitted 6/7/2021 APPLICANT
Assigned to Plan Check Engineer 6/24/2021 JOE VO
Corrections Issued 6/27/2021 JOE VO
Quality Review Completed 7/6/2021 MICHAEL PEREZ
Applicant returned to address corrections 9/15/2021 JOE VO
Plan Check Approved 11/18/2021 JOE VO
Issued 12/1/2021 APPLICANT
Permit Finaled 12/9/2022 KATY RAMIREZ

Permit Application Clearance Information

Green Code Cleared 10/18/2021 JOE VO
DAS Clearance Cleared 11/2/2021 JOE VO
Fire Marshal Fire Life Safety Cleared 11/24/2021 VIDAL GARCIA

Contact Information

Contractor Warner Constructors Inc; Lic. No.: 463497-B 6333 SAN FERNANDO ROAD      GLENDALE, CA 91201

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 1/20/2022 Partial Approval TIMOTHY BUXTON
Drywall Nailing 1/28/2022 Partial Approval TIMOTHY BUXTON
Light Gage Steel Frame 1/28/2022 Approved TIMOTHY BUXTON
Drywall Nailing 2/8/2022 Partial Approval TIMOTHY BUXTON
Light Gage Steel Frame 2/17/2022 Not Ready for Inspection JONATHAN QUACH
Drywall Nailing 2/22/2022 Partial Approval TIMOTHY BUXTON
Light Gage Steel Frame 2/22/2022 Approved TIMOTHY BUXTON
Drywall Nailing 3/2/2022 Partial Approval TIMOTHY BUXTON
Interior/Exterior Lathing 3/2/2022 Approved TIMOTHY BUXTON
Drywall Nailing 3/15/2022 Partial Approval TIMOTHY BUXTON
Drywall Nailing 3/24/2022 Not Ready for Inspection DARRYL ARNOLD
Drywall Nailing 3/25/2022 Approved DARRYL ARNOLD
Final 12/9/2022 Permit Finaled KATY RAMIREZ
Green Building Final 12/9/2022 Approved KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 12/9/2022 SGSOV No Gas KATY RAMIREZ
Smoke Detectors 12/9/2022 Approved KATY RAMIREZ