1946 W FLORENCE AVE 90047
Certificate Information: 1946 W FLORENCE AVE 90047
- Application / Permit
- 21016-10000-14359
- Plan Check / Job No.
- B21LA10448
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan : 25625 Soft-Story seismic retrofit per LABC Chapter 93: SOFT STORY SEISMIC REINFORCEMENT PER DIV. 93 AT BUILDING PARKING GARAGE USING (1) SPECIAL CANTILEVERED COLUMN WITH GRADE BEAM.
- Permit Issued
- Issued on 10/19/2021
- Issuing Office
- Current Status
- CofC Issued on 1/18/2022
Permit Application Status History
| Submitted | 6/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2021 | VARAND SARKISIAN |
| Corrections Issued | 7/12/2021 | VARAND SARKISIAN |
| Quality Review Completed | 7/15/2021 | HANS SANTIAGO |
| Applicant returned to address corrections | 7/29/2021 | VARAND SARKISIAN |
| Plan Check Approved | 9/29/2021 | VARAND SARKISIAN |
| Issued | 10/19/2021 | APPLICANT |
| OK for CofC | 1/12/2022 | DARRYL ARNOLD |
| CofC Issued | 1/18/2022 | WINSTON DUNNING |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 7/21/2021 | RAFAEL FONTES |
| Historic Resource Verification | Cleared | 7/22/2021 | MICAELA TORRES-GIL |
| Community Plan Implem. Overlay | Cleared | 7/28/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2021 | JEANIE LAM |
| Redevelopment Project Area | Cleared | 7/30/2021 | DAVID URITA |
| Tenant Habitability Plan | Cleared | 10/18/2021 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Cal - Quake Construction Inc; Lic. No.: 759817-B | 636 NORTH FORMOSA AVENUE LOS ANGELES, CA 90036 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/23/2021 | Conditional Approval | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 12/3/2021 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 12/3/2021 | Conditional Approval | DARRYL ARNOLD |
| Deputy Other (see comments) | 12/8/2021 | Conditional Approval | DARRYL ARNOLD |
| Excavation/Setback/Form/Re-Bar | 12/8/2021 | Approved | DARRYL ARNOLD |
| Structural Steel Frame | 12/8/2021 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 12/8/2021 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 12/22/2021 | Conditional Approval | DARRYL ARNOLD |
| Final | 1/12/2022 | OK for CofC | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 1/12/2022 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 1/12/2022 | Approved | DARRYL ARNOLD |
| Special/Order Compliance | 1/14/2022 | Corrections Issued | DARRYL ARNOLD |