333 N MISSION ROAD 90033
Certificate Information: 333 N MISSION ROAD 90033
- Application / Permit
- 21016-10000-14231
- Plan Check / Job No.
- B21LA10334
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- CHANGE OF USE OF (E) 8,453 SQ FT, TYPE IIIB, WAREHOUSE TO (N) BASKETBALL TRAINING WITH NO SPECTATORS. (N) ADA COMPLIANT STAIRS AND RESTROOMS.
- Permit Issued
- Issued on 10/13/2021
- Issuing Office
- Current Status
- Issued on 10/13/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2021 | KESETE HAREGOT |
| Corrections Issued | 7/15/2021 | KESETE HAREGOT |
| Quality Review Completed | 7/23/2021 | ALLEN MANALANSAN |
| Building Plans Picked Up | 7/27/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 9/21/2021 | APPLICANT |
| Plan Check Approved | 10/13/2021 | KESETE HAREGOT |
| Issued | 10/13/2021 | APPLICANT |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 8/5/2021 | RICHARD REASER |
| Historic Resource Verification | Cleared | 8/5/2021 | DAVID URITA |
| Redevelopment Project Area | Cleared | 8/5/2021 | DAVID URITA |
| ZI | Cleared | 8/5/2021 | RICHARD REASER |
| ZI | Cleared | 8/5/2021 | RICHARD REASER |
| Eng Process Fee Ord 176,300 | Cleared | 9/16/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 9/16/2021 | STEVE MELGAR |
| DAS Clearance | Cleared | 9/20/2021 | KESETE HAREGOT |
Contact Information
| Contractor | Rjb Builders Inc; Lic. No.: 984546-B | 1232 N FAIROAKS AVE STE 10A PASADENA, CA 91103 |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 10/15/2021 | No Access for Inspection | MARK FERRARI |
| Deputy Drilled-In Anchors | 11/4/2021 | Conditional Approval | KATY RAMIREZ |
| Light Gage Steel Frame | 11/4/2021 | Not Ready for Inspection | KATY RAMIREZ |
| Light Gage Steel Frame | 12/15/2021 | Approved | MARK FERRARI |
| Special/Order Compliance | 2/20/2026 | Corrections Issued | RONALD JIMENEZ |