4233 W 59TH ST 90043

Certificate Information: 4233 W 59TH ST 90043

Application / Permit
21016-10000-14217
Plan Check / Job No.
B21LA10327
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion of existing garage to ADU
Permit Issued
Issued on 8/23/2021
Issuing Office
Current Status
CofO Issued on 2/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/2/2021 APPLICANT
Assigned to Plan Check Engineer 6/2/2021 LARRY LEE
Corrections Issued 6/2/2021 LARRY LEE
Applicant returned to address corrections 6/22/2021 LARRY LEE
Plan Check Approved 8/11/2021 LARRY LEE
Issued 8/23/2021 APPLICANT
CofO in Progress 2/17/2022 HORACE FULTZ
CofO Issued 2/17/2022 DEROLD HAUFF
Permit Finaled 2/17/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/10/2021 RENZ SORIANO
Roof/Waste drainage to street Cleared 6/10/2021 RENZ SORIANO
Sewer availability Cleared 6/24/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 6/25/2021 RENZ SORIANO
Construction near power lines Cleared 8/3/2021 RIDWAN HARDY

Contact Information

Architect Best,, Richard Allen; Lic. No.: C17334 1275 BEVERLY ESTATES DR.      BEVERLY HILLS, CA 90210

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/30/2021 Partial Approval FREDDIE RIVERA
Pre-Inspection 8/30/2021 Corrections Issued FREDDIE RIVERA
Sewer 8/30/2021 Approved FREDDIE RIVERA
Underground Mechanical 8/30/2021 Partial Approval FREDDIE RIVERA
ELECTRICAL-Rough 11/2/2021 Approved FREDDIE RIVERA
HVAC-Rough 11/2/2021 Approved FREDDIE RIVERA
Insulation 11/2/2021 Approved FREDDIE RIVERA
Interior/Exterior Lathing 11/2/2021 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 11/2/2021 Approved FREDDIE RIVERA
Wood Frame 11/2/2021 Approved FREDDIE RIVERA
Drywall Nailing 11/5/2021 Corrections Issued JUSTIN HAWLEY
Drywall Nailing 11/10/2021 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 1/12/2022 Approved FREDDIE RIVERA
ELECTRICAL-Final 1/12/2022 Not Ready for Inspection FREDDIE RIVERA
Final 1/12/2022 Corrections Issued FREDDIE RIVERA
Green Building Final 1/12/2022 Not Ready for Inspection FREDDIE RIVERA
Green Building Rough 1/12/2022 Approved FREDDIE RIVERA
HVAC-Final 1/12/2022 Approved FREDDIE RIVERA
METHANE-Final 1/12/2022 Approved FREDDIE RIVERA
METHANE-Rough 1/12/2022 Approved FREDDIE RIVERA
PLUMBING-Final 1/12/2022 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 1/12/2022 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 1/12/2022 Approved FREDDIE RIVERA
ELECTRICAL-Final 2/16/2022 Approved FREDDIE RIVERA
Final 2/16/2022 OK to Issue CofO FREDDIE RIVERA
Green Building Final 2/16/2022 Approved FREDDIE RIVERA
HVAC-Final 2/16/2022 Approved FREDDIE RIVERA
PLUMBING-Final 2/16/2022 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 2/16/2022 SGSOV Approved FREDDIE RIVERA
Service/Power Release 2/16/2022 Approved FREDDIE RIVERA