4660 W WASHINGTON BLVD 90016
Certificate Information: 4660 W WASHINGTON BLVD 90016
- Application / Permit
- 21016-10000-13709
- Plan Check / Job No.
- B21LA10009
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- Change of use from Retail to Coffee Shop. No Construction. Hours of operation will be from 7:00 am to 11:00 pm.
- Permit Issued
- Issued on 8/23/2021
- Issuing Office
- Current Status
- CofO Issued on 5/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/22/2021 | SALVADOR QUINTANILLA |
| Corrections Issued | 6/22/2021 | SALVADOR QUINTANILLA |
| Plan Check Approved | 8/23/2021 | SALVADOR QUINTANILLA |
| Issued | 8/23/2021 | APPLICANT |
| CofO in Progress | 5/4/2022 | RUSSELL BONVOULOIR |
| CofO Issued | 5/4/2022 | ERNESTO CORRAL |
| Permit Finaled | 5/4/2022 | ERNESTO CORRAL |
Permit Application Clearance Information
| Food Service Establishment | Cleared | 6/24/2021 | PAWAN VERMA |
| Redevelopment Project Area | Cleared | 6/30/2021 | DAVID URITA |
| Eng Process Fee Ord 176,300 | Cleared | 7/1/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 7/1/2021 | RENZ SORIANO |
| Community Plan Implem. Overlay | Cleared | 7/14/2021 | KYLE WINSTON |
| Comm Cor/Mini-Mall | Cleared | 7/15/2021 | DANIEL CORONADO |
| Food establishment approval | Cleared | 8/20/2021 | LACDHS APPROVED |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/30/2021 | Not Ready for Inspection | KATY RAMIREZ |
| Pre-Inspection | 11/30/2021 | Corrections Issued | KATY RAMIREZ |
| Drywall Nailing | 12/3/2021 | Partial Approval | KATY RAMIREZ |
| Footing/Foundation/Slab | 12/6/2021 | Partial Approval | KATY RAMIREZ |
| Wood Frame | 2/3/2022 | Partial Approval | KATY RAMIREZ |
| Wood Frame | 2/15/2022 | Approved | KATY RAMIREZ |
| Final | 4/13/2022 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| SGSOV-Seismic Gas S/O Valve | 4/13/2022 | SGSOV Approved | RUSSELL BONVOULOIR |
| Smoke Detectors | 4/13/2022 | Approved | RUSSELL BONVOULOIR |
| Final | 4/29/2022 | Partial Inspection | KATY RAMIREZ |
| Final | 5/4/2022 | OK to Issue CofO | RUSSELL BONVOULOIR |