5145 N NEWCASTLE AVE 91316

Certificate Information: 5145 N NEWCASTLE AVE 91316

Application / Permit
21016-10000-13579
Plan Check / Job No.
B21LA09913
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert the existing 18ft x 20 ft detached garage to an Accessory Dwelling Unit. Per Ordinance 186481
Permit Issued
Issued on 6/15/2021
Issuing Office
Current Status
CofO Issued on 1/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/25/2021 APPLICANT
Assigned to Plan Check Engineer 5/31/2021 HERNAN ARREOLA
Corrections Issued 5/31/2021 HERNAN ARREOLA
Plan Check Approved 6/8/2021 HERNAN ARREOLA
Issued 6/15/2021 APPLICANT
CofO in Progress 12/22/2021 DAVID SANDOVAL
CofO Issued 1/6/2022 MICHAEL SMITH
Permit Finaled 1/6/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 6/8/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/8/2021 CARLOS AGUILERA
Sewer availability Cleared 6/8/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/1/2021 Approved DAVID SANDOVAL
Footing/Foundation/Slab 7/1/2021 Corrections Issued DAVID SANDOVAL
PLUMBING-Rough 7/1/2021 Partial Approval DAVID SANDOVAL
BUILDING-Rough-Frame 7/7/2021 Not Ready for Inspection DAVID SANDOVAL
Footing/Foundation/Slab 7/7/2021 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 7/22/2021 Corrections Issued KRISTEN CAUSEY
ELECTRICAL-Rough 7/22/2021 Corrections Issued RYAN SALAZAR
Green Building Rough 7/22/2021 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 7/22/2021 Corrections Issued ALIZAH MAYAGOITIA
Special/Order Compliance 7/22/2021 Partial Inspection MICHAEL PELHAM
HVAC-Rough 7/29/2021 Corrections Issued RONALD COWAN
BUILDING-Rough-Frame 8/5/2021 Not Ready for Inspection DAVID SANDOVAL
ELECTRICAL-Rough 8/5/2021 Corrections Issued DAVID SANDOVAL
HVAC-Rough 8/5/2021 Corrections Issued DAVID SANDOVAL
PLUMBING-Rough 8/5/2021 Not Ready for Inspection DAVID SANDOVAL
ELECTRICAL-Rough 8/10/2021 Approved DAVID SANDOVAL
HVAC-Rough 8/10/2021 Not Ready for Inspection DAVID SANDOVAL
Insulation 8/10/2021 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 8/10/2021 Approved DAVID SANDOVAL
Underground Mechanical 8/10/2021 Partial Inspection DAVID SANDOVAL
BUILDING-Rough-Frame 8/13/2021 Not Ready for Inspection DAVID SANDOVAL
HVAC-Rough 8/13/2021 Approved DAVID SANDOVAL
Insulation 8/13/2021 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 8/19/2021 Approved DAVID SANDOVAL
Green Building Rough 8/19/2021 Approved DAVID SANDOVAL
Interior/Exterior Lathing 8/19/2021 Partial Approval DAVID SANDOVAL
Shower Pan 8/19/2021 Approved DAVID SANDOVAL
Drywall Nailing 8/20/2021 Approved DAVID SANDOVAL
ELECTRICAL-Final 12/13/2021 Approved DAVID SANDOVAL
Final 12/13/2021 Corrections Issued DAVID SANDOVAL
HVAC-Final 12/13/2021 Approved DAVID SANDOVAL
PLUMBING-Final 12/13/2021 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 12/13/2021 SGSOV Not Ready DAVID SANDOVAL
Smoke Detectors 12/13/2021 Approved DAVID SANDOVAL
Final 12/16/2021 Partial Approval DAVID SANDOVAL
Gas Test 12/16/2021 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 12/16/2021 SGSOV Approved DAVID SANDOVAL
Final 12/22/2021 OK to Issue CofO DAVID SANDOVAL