1627 1/2 W LEIGHTON AVE 90062

Certificate Information: 1627 1/2 W LEIGHTON AVE 90062

Application / Permit
21016-10000-13574
Plan Check / Job No.
B21LA09911
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) garage to ADU. 18'x19' per Ordinance 186481
Permit Issued
Issued on 8/18/2021
Issuing Office
Current Status
CofO Issued on 3/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/24/2021 APPLICANT
Assigned to Plan Check Engineer 6/1/2021 HERNAN ARREOLA
Corrections Issued 6/1/2021 HERNAN ARREOLA
Plan Check Approved 8/15/2021 HERNAN ARREOLA
Issued 8/18/2021 APPLICANT
CofO in Progress 3/15/2022 HORACE FULTZ
Permit Finaled 3/16/2022 DEROLD HAUFF
CofO Issued 3/16/2022 DEROLD HAUFF
Permit Finaled 3/16/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/22/2021 JEREMY CHOK
Sewer availability Cleared 6/22/2021 JEREMY CHOK
Construction near power lines Cleared 8/10/2021 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 8/11/2021 JEREMY CHOK

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/22/2021 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 9/28/2021 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 10/4/2021 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 10/13/2021 Approved SABAS ALONSO
BUILDING-Rough-Frame 11/1/2021 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 11/19/2021 Approved SABAS ALONSO
ELECTRICAL-Rough 11/19/2021 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 11/19/2021 Approved SABAS ALONSO
PLUMBING-Rough 11/19/2021 Approved SABAS ALONSO
Insulation 11/29/2021 Partial Approval JUSTIN HAWLEY
Interior/Exterior Lathing 11/29/2021 Approved JUSTIN HAWLEY
Drywall Nailing 12/7/2021 Corrections Issued SABAS ALONSO
ELECTRICAL-Final 12/7/2021 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 12/13/2021 Approved FREDDIE RIVERA
Drywall Nailing 1/18/2022 Approved SABAS ALONSO
ELECTRICAL-Final 1/18/2022 Not Ready for Inspection SABAS ALONSO
Final 1/18/2022 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 1/18/2022 Approved SABAS ALONSO
Final 3/3/2022 Corrections Issued SABAS ALONSO
Final 3/11/2022 OK to Issue CofO SABAS ALONSO