2260 E 15TH ST 90021
Certificate Information: 2260 E 15TH ST 90021
- Application / Permit
- 21016-10000-13407
- Plan Check / Job No.
- B21LA09773
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- CHANGE OF USE FROM EXISTING WAREHOUSE & MANUFACTURING TO OFFICE ON GROUND FLOOR. TENANT IMPROVEMENT CONSISTS OF BUILDING OFFICES ON GROUND FLOOR, APPROXIMATELY 19,170 SF.
- Permit Issued
- Issued on 3/16/2022
- Issuing Office
- Current Status
- CofO Issued on 2/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2021 | JOE VO |
| Corrections Issued | 6/28/2021 | JOE VO |
| Quality Review Completed | 7/6/2021 | MICHAEL PEREZ |
| Disabled Access Plans Picked Up | 7/20/2021 | APPLICANT |
| Applicant returned to address corrections | 10/14/2021 | JOE VO |
| Plan Check Approved | 12/27/2021 | JOE VO |
| Building Plans Picked Up | 12/28/2021 | APPLICANT |
| Issued | 3/16/2022 | APPLICANT |
| CofO in Progress | 2/27/2024 | RONALD JIMENEZ |
| CofO Issued | 2/28/2024 | ERNESTO CORRAL |
| Permit Finaled | 2/28/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2021 | RENZ SORIANO |
| Green Code | Cleared | 11/22/2021 | JOE VO |
| DAS Clearance | Cleared | 12/7/2021 | JOE VO |
| Sewer availability | Cleared | 12/14/2021 | JEANETTE VONG |
Contact Information
| Contractor | Architectura Design Build Group Inc; Lic. No.: 972248-B | 1736 WESTWOOD BLVD STE 201 LOS ANGELES, CA 90024 |
| Engineer | Mourad,, Daniel; Lic. No.: C83387 | 542 N FULLER AVE LOS ANGELES, CA 90036 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/23/2022 | Partial Inspection | MARK FERRARI |
| Drywall Nailing | 4/21/2023 | Partial Inspection | JULIAN CAPUCETTI |
| Light Gage Steel Frame | 4/21/2023 | Partial Inspection | JULIAN CAPUCETTI |
| Posting Pre-Inspection | 4/21/2023 | Partial Inspection | JULIAN CAPUCETTI |
| Verify Rec and Parks Fee Memo | 4/21/2023 | Partial Inspection | JULIAN CAPUCETTI |
| Wood Frame | 4/21/2023 | Partial Inspection | JULIAN CAPUCETTI |
| Final | 10/6/2023 | Corrections Issued | KATY RAMIREZ |
| Drywall Nailing | 2/21/2024 | Approved | RONALD JIMENEZ |
| Light Gage Steel Frame | 2/21/2024 | Approved | RONALD JIMENEZ |
| Final | 2/23/2024 | Conditional Approval | RONALD JIMENEZ |
| METHANE-Final | 2/23/2024 | Approved | RONALD JIMENEZ |
| METHANE-Rough | 2/23/2024 | Approved | RONALD JIMENEZ |
| Reinforced Masonry Frame | 2/23/2024 | Approved | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 2/23/2024 | SGSOV Approved | RONALD JIMENEZ |
| Smoke Detectors | 2/23/2024 | Approved | RONALD JIMENEZ |
| Final | 2/27/2024 | OK to Issue CofO | RONALD JIMENEZ |