3225 N FLETCHER DR 90065

Certificate Information: 3225 N FLETCHER DR 90065

Application / Permit
21016-10000-13406
Plan Check / Job No.
B21LA09770
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(18) Day Care Facility adults
Work Description
CHANGE OF USE FROM OFFICE TO ADULT DAY CARE
Permit Issued
Issued on 9/12/2022
Issuing Office
Metro
Current Status
CofO Issued on 2/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/21/2021 APPLICANT
Assigned to Plan Check Engineer 7/1/2021 ARSALAN SHABESTARI
Corrections Issued 7/8/2021 ARSALAN SHABESTARI
Quality Review Completed 7/19/2021 MICHAEL PEREZ
Building Plans Picked Up 7/30/2021 APPLICANT
Green Plans Picked Up 10/5/2021 APPLICANT
Applicant returned to address corrections 2/24/2022 ARSALAN SHABESTARI
Plan Check Approved 9/7/2022 ARSALAN SHABESTARI
Issued 9/12/2022 APPLICANT
CofO in Progress 2/19/2025 RAMAZANALI ALMASI
CofO Issued 2/19/2025 ERNESTO CORRAL
Permit Finaled 2/19/2025 ERNESTO CORRAL

Permit Application Clearance Information

Supp. Use District POD/CDO/TDO Cleared 7/14/2021 ADRINEH MELKONIAN
"Q" conditions Cleared 7/16/2021 MAXFIELD VERMY
Green Code Cleared 10/5/2021 AARON COSTA
DAS Clearance Cleared 3/4/2022 ARSALAN SHABESTARI
Eng Process Fee Ord 176,300 Cleared 7/6/2022 WALLIE JONG
Sewer availability Cleared 7/6/2022 WALLIE JONG
Fire Marshal Fire Life Safety Cleared 7/15/2022 ANDREW KO
Food Service Establishment Cleared 7/29/2022 RAMESHBHAIR PATEL
Food establishment approval Cleared 9/7/2022 LACDHS APPROVED

Contact Information

Architect Saroian,, Varoozh; Lic. No.: C13791 128 S KENWOOD STREET      GLENDALE, CA 91205
Contractor Aladdin Construction; Lic. No.: 677011-B 9740 LA CANADA WAY      SHADOW HILLS, CA 91040

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 1/10/2023 Corrections Issued RAFAEL CORTES
Drywall Nailing 1/17/2023 Approved RAFAEL CORTES
Light Gage Steel Frame 1/17/2023 Partial Approval RAFAEL CORTES
Drywall Nailing 1/23/2023 Partial Approval RAFAEL CORTES
Deputy Drilled-In Anchors 3/20/2023 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 3/20/2023 Approved RAFAEL CORTES
Deputy Reinf. Concrete 3/21/2023 Conditional Approval MICHAEL ROSENBERG
Light Gage Steel Frame 3/29/2023 Partial Approval RAFAEL CORTES
Drywall Nailing 4/3/2023 Partial Approval RAFAEL CORTES
Light Gage Steel Frame 6/14/2023 Partial Approval RAFAEL CORTES
Drywall Nailing 6/20/2023 Approved JULIAN CAPUCETTI
Final 8/17/2023 Not Ready for Inspection RAFAEL CORTES
Green Building Final 8/17/2023 Not Ready for Inspection RAFAEL CORTES
Green Building Rough 8/17/2023 Approved RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 8/17/2023 SGSOV Not Ready RAFAEL CORTES
Smoke Detectors 8/17/2023 Not Ready for Inspection RAFAEL CORTES
T-Bar Ceiling 8/17/2023 Partial Approval RAFAEL CORTES
Wood Frame 8/17/2023 Approved RAFAEL CORTES
T-Bar Ceiling 8/21/2023 Approved RONALD JIMENEZ
Final 7/15/2024 Not Ready for Inspection RONALD JIMENEZ
Green Building Final 7/15/2024 Approved RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 7/15/2024 SGSOV Approved RONALD JIMENEZ
Smoke Detectors 7/15/2024 Not Ready for Inspection RONALD JIMENEZ
Final 12/17/2024 Not Ready for Inspection RAMAZANALI ALMASI
Smoke Detectors 12/17/2024 Approved RAMAZANALI ALMASI
Final 2/13/2025 Conditional Approval RAMAZANALI ALMASI
Final 2/19/2025 OK to Issue CofO RAMAZANALI ALMASI