6429 W WYNKOOP ST 90045

Certificate Information: 6429 W WYNKOOP ST 90045

Application / Permit
21016-10000-13259
Plan Check / Job No.
B21LA09678
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EXISTING DETACHED GARAGE TO BE CONVERTED INTO AN ADU PER LAMC 12.22A33.FULLY SPRINKLERED.
Permit Issued
Issued on 3/15/2022
Issuing Office
Current Status
CofO Issued on 1/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/7/2021 APPLICANT
Assigned to Plan Check Engineer 6/8/2021 SAMUEL GONZALEZ
Corrections Issued 6/8/2021 SAMUEL GONZALEZ
Plan Check Approved 9/30/2021 SAMUEL GONZALEZ
Issued 3/15/2022 APPLICANT
Building Plans Picked Up 3/17/2022 APPLICANT
CofO in Progress 1/10/2023 HERBERT GIRON
Permit Finaled 1/18/2023 DANIEL ORRANTE
CofO Issued 1/18/2023 DANIEL ORRANTE
Permit Finaled 1/18/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 7/6/2021 DENNIS BRAGIN
Roof/Waste drainage to street Cleared 7/6/2021 DENNIS BRAGIN
Sewer availability Cleared 7/6/2021 DENNIS BRAGIN
Eng Process Fee Ord 176,300 Cleared 7/15/2021 DINAH GARIN
Construction near power lines Cleared 8/16/2021 WALTER RAMIREZ
Hydrant and Access approval Cleared 9/13/2021 KURT CORRAL

Contact Information

Contractor O'Riordan Niall; Lic. No.: 904668-B 578 WASHINGTON BOULEVARD #204      MARINA DEL REY, CA 90252

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/14/2022 Partial Approval JESUS RODRIGUEZ
Sewer 4/14/2022 Approved JESUS RODRIGUEZ
Underground Mechanical 4/29/2022 Conditional Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 5/6/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 5/24/2022 Approved BOBBY KEY
PLUMBING-Rough 5/24/2022 Approved BOBBY KEY
Underground Mechanical 5/24/2022 Approved BOBBY KEY
Green Building Rough 6/7/2022 Approved BOBBY KEY
HVAC-Rough 6/7/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 6/13/2022 Conditional Approval STEPHANIE SWANSON
Insulation 6/13/2022 Corrections Issued STEPHANIE SWANSON
Insulation 6/15/2022 Conditional Approval RICHARD STEINBACH
Drywall Nailing 6/21/2022 Conditional Approval DAVID FEILER
Interior/Exterior Lathing 6/30/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 8/5/2022 Approved HERBERT GIRON
Interior/Exterior Lathing 8/5/2022 Approved HERBERT GIRON
Drywall Nailing 9/15/2022 Approved HERBERT GIRON
ELECTRICAL-Final 9/15/2022 Corrections Issued HERBERT GIRON
Final 9/15/2022 Corrections Issued HERBERT GIRON
HVAC-Final 9/15/2022 Corrections Issued HERBERT GIRON
PLUMBING-Final 9/15/2022 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 9/15/2022 SGSOV Approved HERBERT GIRON
Smoke Detectors 9/15/2022 Approved HERBERT GIRON
ELECTRICAL-Final 10/3/2022 Approved HERBERT GIRON
Gas Test 10/3/2022 Approved HERBERT GIRON
Green Building Final 10/3/2022 Approved HERBERT GIRON
PLUMBING-Final 10/3/2022 Approved HERBERT GIRON
Final 1/10/2023 OK to Issue CofO HERBERT GIRON
HVAC-Final 1/10/2023 Approved HERBERT GIRON