332 N OAKHURST DR #105 90048
Certificate Information: 332 N OAKHURST DR #105 90048
- Application / Permit
- 21016-10000-13152
- Plan Check / Job No.
- B21LA09562
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW GARAGE DOOR OPENINGS AT GROUND FLOOR GARAGE. ENCLOSE EXISTING [11'1" x 8'5"] COVERED PORCH AT SECOND FLOOR DWELLING UNIT AND RECONFIGURE INTERIOR FLOOR PLAN. ALTERATIONS TO EXTERIOR WALLS FOR INFILL AND NEW OPENINGS. FIRE SPRINKLERS TO BE INSTALLED IN BUILDING
- Permit Issued
- Issued on 10/8/2021
- Issuing Office
- Current Status
- Permit Finaled on 3/3/2023
Permit Application Status History
| Submitted | 5/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/21/2021 | FERNANDO FLORES |
| Corrections Issued | 5/22/2021 | FERNANDO FLORES |
| Building Plans Picked Up | 5/26/2021 | APPLICANT |
| Applicant returned to address corrections | 7/13/2021 | JESSE JIMENEZ |
| Applicant returned to address corrections | 8/6/2021 | GEORGE ALVAREZ |
| Plan Check Approved | 10/6/2021 | FERNANDO FLORES |
| Issued | 10/8/2021 | APPLICANT |
| Permit Finaled | 2/28/2023 | ALFREDO LOPEZ |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/4/2021 | CECILIO NAVARRO |
| Tenant Habitability Plan | Cleared | 6/7/2021 | MICHAEL SOTO |
| Roof/Waste drainage to street | Cleared | 6/9/2021 | CECILIO NAVARRO |
| "Q" conditions | Cleared | 6/22/2021 | ANACANY HURTADO |
Contact Information
| Architect | Tsai,, Kuo-Huei; Lic. No.: C33710 | 834 S BROADWAY SUITE 1206 LOS ANGELES, CA 90014 |
| Contractor | Etco Homes Inc; Lic. No.: 879789-B | 8447 WILSHIRE BLVD #400 BEVERLY HILLS, CA 902113209 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/21/2021 | Approved | KATY RAMIREZ |
| Wood Frame | 12/8/2021 | Partial Approval | BRUCE CAMPBELL |
| BUILDING-Rough-Frame | 1/27/2022 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Rough | 1/27/2022 | Corrections Issued | CRAIG DAVIS |
| HVAC-Rough | 1/27/2022 | Approved | CRAIG DAVIS |
| Insulation | 1/27/2022 | Not Ready for Inspection | CRAIG DAVIS |
| PLUMBING-Rough | 1/27/2022 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Rough | 2/14/2022 | Approved | EVAN COOPER |
| Green Building Rough | 2/14/2022 | Approved | EVAN COOPER |
| PLUMBING-Rough | 2/14/2022 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 2/14/2022 | Approved | EVAN COOPER |
| Wood Frame | 2/14/2022 | Approved | EVAN COOPER |
| Insulation | 2/22/2022 | Approved | EVAN COOPER |
| Drywall Nailing | 2/28/2022 | Partial Approval | EVAN COOPER |
| Drywall Nailing | 3/15/2022 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 6/27/2022 | No Access for Inspection | EVAN COOPER |
| Service/Power Release | 6/29/2022 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 7/5/2022 | No Access for Inspection | EVAN COOPER |
| PLUMBING-Final | 7/5/2022 | No Access for Inspection | EVAN COOPER |
| ELECTRICAL-Final | 7/19/2022 | Approved | EVAN COOPER |
| HVAC-Final | 7/19/2022 | Corrections Issued | EVAN COOPER |
| PLUMBING-Final | 7/19/2022 | Corrections Issued | EVAN COOPER |
| Final | 7/22/2022 | Corrections Issued | EVAN COOPER |
| METHANE-Final | 7/22/2022 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 7/22/2022 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 7/22/2022 | Approved | EVAN COOPER |
| Final | 2/28/2023 | Permit Finaled | ALFREDO LOPEZ |