63 E MARKET ST 90291
Certificate Information: 63 E MARKET ST 90291
- Application / Permit
- 21016-10000-12984
- Plan Check / Job No.
- B21LA09471
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- EXTERIOR & INTRERIOT CORE & SHELL T.I TO (E) TWO-STORY OFFICE BUILDING INCLUDING NEW STAIRS, RAMPS & EGRESS CIRCULATION &NEW INTERIOR STRUCTURAL WORK & ROOF REPAIR
- Permit Issued
- Issued on 11/4/2021
- Issuing Office
- Current Status
- Permit Finaled on 12/1/2022
Permit Application Status History
| Submitted | 5/19/2021 | APPLICANT |
| Green Plans Picked Up | 6/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2021 | GARO TELMI |
| Disabled Access Plans Picked Up | 7/6/2021 | APPLICANT |
| Corrections Issued | 7/9/2021 | GARO TELMI |
| Quality Review Completed | 7/20/2021 | MICHAEL PEREZ |
| Building Plans Picked Up | 7/22/2021 | APPLICANT |
| Applicant returned to address corrections | 9/2/2021 | GARO TELMI |
| Applicant returned to address corrections | 9/21/2021 | GARO TELMI |
| Plan Check Approved | 10/29/2021 | GARO TELMI |
| Issued | 11/4/2021 | APPLICANT |
| Permit Finaled | 12/1/2022 | SORIN CIRSTOIU |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/13/2021 | SAUL GARCIA |
| ZA Case | Cleared | 8/13/2021 | DANIEL CORONADO |
| Work Adjacent to Public Way | Cleared | 8/17/2021 | SAUL GARCIA |
| Green Code | Cleared | 9/2/2021 | AARON COSTA |
| DAS Clearance | Cleared | 9/9/2021 | EDDIE GARIN |
| Coastal Zone | Cleared | 10/1/2021 | DANIEL CORONADO |
| Specific Plan | Cleared | 10/26/2021 | SIENNA KUO |
Contact Information
| Architect | Loescher,, Karl Benjamin; Lic. No.: C30490 | 353 S. BROADWAY #201 LOS ANGELES, CA 90013 |
| Contractor | J T M Construction Group Inc; Lic. No.: 956584-B | 44 WEST 28TH STREET 11TH FLOOR NEW YORK, NY 10001 |
| Engineer | Woodgate,, Jeremy Paul; Lic. No.: S4858 | 44748 SW KNIGHT RD GASTON, OR 97119 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 11/18/2021 | Approved | NICK LAROCCA |
| Footing/Foundation/Slab | 11/18/2021 | Partial Approval | NICK LAROCCA |
| Deputy Steel/Welding | 12/7/2021 | Conditional Approval | NICK LAROCCA |
| Deputy Reinf. Concrete | 12/8/2021 | Approved | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 12/8/2021 | Partial Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 12/8/2021 | Partial Approval | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 12/9/2021 | Partial Inspection | JOHN DODGE |
| Footing/Foundation/Slab | 12/9/2021 | Partial Inspection | JOHN DODGE |
| Deputy Reinf. Concrete | 12/16/2021 | Approved | JOEY BUCHANAN |
| Footing/Foundation/Slab | 1/6/2022 | Partial Approval | JOHN DODGE |
| Reinforced Concrete Frame | 1/6/2022 | Not Ready for Inspection | JOHN DODGE |
| Excavation/Setback/Form/Re-Bar | 1/24/2022 | Not Ready for Inspection | JOHN DODGE |
| Footing/Foundation/Slab | 1/24/2022 | Not Ready for Inspection | JOHN DODGE |
| Excavation/Setback/Form/Re-Bar | 1/26/2022 | Approved | JOEY BUCHANAN |
| Footing/Foundation/Slab | 1/26/2022 | Approved | JOEY BUCHANAN |
| Footing/Foundation/Slab | 3/29/2022 | Not Ready for Inspection | JOHN DODGE |
| Footing/Foundation/Slab | 3/30/2022 | Not Ready for Inspection | NICK LAROCCA |
| Light Gage Steel Frame | 7/14/2022 | Partial Approval | SORIN CIRSTOIU |
| Structural Steel Frame | 7/14/2022 | Partial Approval | SORIN CIRSTOIU |
| Final | 11/29/2022 | Partial Inspection | SORIN CIRSTOIU |
| Green Building Final | 11/29/2022 | Approved | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 11/29/2022 | SGSOV Approved | SORIN CIRSTOIU |
| Smoke Detectors | 11/29/2022 | Approved | SORIN CIRSTOIU |
| Final | 12/1/2022 | Permit Finaled | SORIN CIRSTOIU |