5725 W CAMERFORD AVE 90038

Certificate Information: 5725 W CAMERFORD AVE 90038

Application / Permit
21016-10000-12905
Plan Check / Job No.
B21LA09417
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Eplan: Soft-Story seismic retrofit per LABC Chapter 93: INSTALL THREE CANTILEVER COLUMNS AND ONE MOMENT FRAME
Permit Issued
Issued on 8/4/2021
Issuing Office
Current Status
CofC Issued on 1/11/2022

Permit Application Status History

Submitted 5/18/2021 APPLICANT
Assigned to Plan Check Engineer 6/3/2021 HANS SANTIAGO
Corrections Issued 6/7/2021 HANS SANTIAGO
Quality Review Completed 6/9/2021 SAI KHUM
Plan Check Approved 7/14/2021 ANDREW SANTIAGO
Issued 8/4/2021 APPLICANT
OK for CofC 11/18/2021 MARK FERRARI
CofC Issued 1/11/2022 WINSTON DUNNING

Permit Application Clearance Information

Tenant Habitability Plan Cleared 8/3/2021 PHILLIP MUNGUIA

Contact Information

Contractor Courteous Construction Co Inc; Lic. No.: 567324-B P O BOX 9287      GLENDALE, CA 91226
Engineer Rezazadeh,, Mehdi; Lic. No.: C49626 P O BOX 98      DANVILLE, CA 94526

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 8/30/2021 Partial Approval BRUCE CAMPBELL
Wood Frame 9/2/2021 Partial Approval BRUCE CAMPBELL
Deputy Drilled-In Anchors 9/8/2021 Conditional Approval BRUCE CAMPBELL
Excavation/Setback/Form/Re-Bar 9/8/2021 Partial Approval BRUCE CAMPBELL
Footing/Foundation/Slab 9/8/2021 Approved BRUCE CAMPBELL
Deputy Drilled-In Anchors 9/30/2021 Conditional Approval BRUCE CAMPBELL
Excavation/Setback/Form/Re-Bar 9/30/2021 Approved BRUCE CAMPBELL
Footing/Foundation/Slab 9/30/2021 Approved BRUCE CAMPBELL
Structural Steel Frame 9/30/2021 Approved BRUCE CAMPBELL
Wood Frame 9/30/2021 Approved BRUCE CAMPBELL
Deputy Drilled-In Anchors 10/1/2021 Conditional Approval BRUCE CAMPBELL
Deputy Reinf. Concrete 10/5/2021 Conditional Approval BRUCE CAMPBELL
Interior/Exterior Lathing 10/18/2021 Approved BRUCE CAMPBELL
Final 11/1/2021 Corrections Issued BRUCE CAMPBELL
METHANE-Final 11/1/2021 Approved BRUCE CAMPBELL
SGSOV-Seismic Gas S/O Valve 11/1/2021 SGSOV Approved BRUCE CAMPBELL
Smoke Detectors 11/1/2021 Approved BRUCE CAMPBELL
Final 11/18/2021 OK for CofC MARK FERRARI