303 E 5TH ST 3RD FLOOR 90013
Certificate Information: 303 E 5TH ST 3RD FLOOR 90013
- Application / Permit
- 21016-10000-12904
- Plan Check / Job No.
- B21LA09418
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (11) Dormitory
- Work Description
- TENANT IMPROVEMENT OF (E) DORMITORY ON THE 3RD FLOOR. NEW INTERIOR PARTIAL HEIGHT WALLS, NEW FLOORING, NEW CEILING, NEW ELECTRICAL, DEMOLITION OF (E) INTERIOR PARTIAL AND FULL HEIGHT.
- Permit Issued
- Issued on 8/9/2021
- Issuing Office
- Current Status
- Permit Finaled on 8/31/2022
Permit Application Status History
| Submitted | 5/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | KEVIN MORALES |
| Corrections Issued | 6/3/2021 | KEVIN MORALES |
| Quality Review Completed | 6/8/2021 | EUGENE BARBEAU |
| Disabled Access Plans Picked Up | 6/21/2021 | APPLICANT |
| Applicant returned to address corrections | 7/20/2021 | KEVIN MORALES |
| Green Plans Picked Up | 7/30/2021 | APPLICANT |
| Plan Check Approved | 8/6/2021 | KEVIN MORALES |
| Issued | 8/9/2021 | APPLICANT |
| Building Plans Picked Up | 8/17/2021 | APPLICANT |
| Permit Finaled | 8/30/2022 | TIMOTHY BUXTON |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 6/15/2021 | MICAELA TORRES-GIL |
| Redevelopment Project Area | Cleared | 6/23/2021 | GRACIELA ACOSTA |
| Green Code | Cleared | 7/8/2021 | AARON COSTA |
| Fire Marshal Fire Life Safety | Cleared | 7/12/2021 | MENOA AGHAJANI |
| DAS Clearance | Cleared | 8/5/2021 | EUGENE BARBEAU |
Contact Information
| Architect | Wahlroos-Ritter,, Ingalill; Lic. No.: C24938 | 2020 LEMOYNE STREET LOS ANGELES, CA 90026 |
| Contractor | Inland Builders Group Inc; Lic. No.: 806875-B | 31500 GRAPE STREET 3-14 LAKE ELSINORE, CA 92532 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 11/8/2021 | Approved | TIMOTHY BUXTON |
| Drywall Nailing | 11/30/2021 | Approved | TIMOTHY BUXTON |
| T-Bar Ceiling | 11/30/2021 | Partial Approval | TIMOTHY BUXTON |
| Pre-Inspection | 5/10/2022 | Approved | TIMOTHY BUXTON |
| Final | 8/12/2022 | Not Ready for Inspection | TIMOTHY BUXTON |
| Green Building Final | 8/12/2022 | Not Ready for Inspection | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 8/12/2022 | SGSOV No Gas | TIMOTHY BUXTON |
| Smoke Detectors | 8/12/2022 | Approved | TIMOTHY BUXTON |
| Final | 8/30/2022 | Permit Finaled | TIMOTHY BUXTON |
| Green Building Final | 8/30/2022 | Approved | TIMOTHY BUXTON |