7423 N TUJUNGA AVE 91605
Certificate Information: 7423 N TUJUNGA AVE 91605
- Application / Permit
- 21016-10000-12643
- Plan Check / Job No.
- B21LA09273
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) 2-car garage into an ADU.
- Permit Issued
- Issued on 7/22/2021
- Issuing Office
- Current Status
- CofO Issued on 8/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/18/2021 | RAHEL BEYENE |
| Corrections Issued | 5/18/2021 | RAHEL BEYENE |
| Applicant returned to address corrections | 6/17/2021 | ADAM HEGAZI |
| Plan Check Approved | 6/24/2021 | ADAM HEGAZI |
| Issued | 7/22/2021 | APPLICANT |
| Building Plans Picked Up | 7/26/2021 | APPLICANT |
| CofO in Progress | 8/24/2022 | ROBERT GOLD |
| CofO Issued | 8/24/2022 | MICHAEL SMITH |
| Permit Finaled | 8/24/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/19/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 5/19/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 5/26/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/3/2021 | No Access for Inspection | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 8/4/2021 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 8/23/2021 | Approved | DANIEL DREW |
| ELECTRICAL-Rough | 8/23/2021 | Partial Approval | DANIEL DREW |
| Green Building Rough | 8/23/2021 | Not Ready for Inspection | DANIEL DREW |
| PLUMBING-Rough | 8/23/2021 | Approved | DANIEL DREW |
| ELECTRICAL-Rough | 8/25/2021 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 8/25/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 8/27/2021 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 9/1/2021 | Approved | DANIEL DREW |
| Interior/Exterior Lathing | 9/10/2021 | Corrections Issued | LILIANA PORTILLO |
| Shower Pan | 9/10/2021 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 9/21/2021 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 11/5/2021 | Approved | DANIEL DREW |
| Final | 11/5/2021 | Corrections Issued | DANIEL DREW |
| Green Building Final | 11/5/2021 | Approved | DANIEL DREW |
| Green Building Rough | 11/5/2021 | Approved | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 11/5/2021 | SGSOV Not Ready | DANIEL DREW |
| Smoke Detectors | 11/5/2021 | Approved | DANIEL DREW |
| Pre-Inspection | 11/9/2021 | Corrections Issued | MISAEL ESPARZA |
| Final | 11/19/2021 | Corrections Issued | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 11/19/2021 | SGSOV Approved | DANIEL DREW |
| Pre-Inspection | 11/24/2021 | No Access for Inspection | MICHAEL TEMPLE |
| Final | 8/24/2022 | OK to Issue CofO | ROBERT GOLD |