4509 N CORLISS ST 90041

Certificate Information: 4509 N CORLISS ST 90041

Application / Permit
21016-10000-12457
Plan Check / Job No.
B21LA09161
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT PORTION OF LIVING ROOM TO BEDROOM AND ADD NEW RESTROOM. REMODEL KITCHEN. NO EXTERIOR WORK. CONVERT (E) SCREEN PORCH TO BEDROOM.
Permit Issued
Issued on 8/16/2021
Issuing Office
Current Status
Permit Finaled on 12/8/2021

Permit Application Status History

Submitted 5/13/2021 APPLICANT
Assigned to Plan Check Engineer 5/14/2021 FERNANDO FLORES
Corrections Issued 5/17/2021 FERNANDO FLORES
Applicant returned to address corrections 5/22/2021 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 6/2/2021 JESSE JIMENEZ
Applicant returned to address corrections 7/4/2021 TSE MING HUANG
Applicant returned to address corrections 8/1/2021 AUNG SOE
Plan Check Approved 8/16/2021 SHANGQIN XIE
Issued 8/16/2021 APPLICANT
Building Plans Picked Up 8/19/2021 APPLICANT
Permit Finaled 12/7/2021 CRAIG VAUGHAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/28/2021 THOMAS LANG
Sewer availability Cleared 7/28/2021 THOMAS LANG

Contact Information

Contractor Kafe Design & Construction; Lic. No.: 977712-B 317 E RAMONA ROAD      ALHAMBRA, CA 91801

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 8/20/2021 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 8/20/2021 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Rough 8/20/2021 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 8/20/2021 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 8/26/2021 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 8/26/2021 Approved CRAIG VAUGHAN
HVAC-Rough 8/26/2021 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 8/26/2021 Approved CRAIG VAUGHAN
Insulation 8/31/2021 Conditional Approval BRIAN SULLIVAN
Drywall Nailing 9/3/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 9/3/2021 Corrections Issued CRAIG VAUGHAN
HVAC-Rough 9/3/2021 Partial Approval CRAIG VAUGHAN
Shower Pan 9/13/2021 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 9/15/2021 Partial Approval KATHRYN BUTTERWORTH
ELECTRICAL-Final 10/20/2021 Corrections Issued CRAIG VAUGHAN
Final 10/20/2021 Corrections Issued CRAIG VAUGHAN
HVAC-Final 10/20/2021 Approved CRAIG VAUGHAN
PLUMBING-Final 10/20/2021 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 10/20/2021 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 10/20/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Final 12/7/2021 Approved CRAIG VAUGHAN
Final 12/7/2021 Permit Finaled CRAIG VAUGHAN
HVAC-Final 12/7/2021 Approved CRAIG VAUGHAN
PLUMBING-Final 12/7/2021 Approved CRAIG VAUGHAN