2102 1/2 S HILLCREST DR 90016

Certificate Information: 2102 1/2 S HILLCREST DR 90016

Application / Permit
21016-10000-12439
Plan Check / Job No.
B21LA09137
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) GARAGE TO ADU PER PER GCS 65852.2(e)(1)(A) AND PER WFPP
Permit Issued
Issued on 6/23/2021
Issuing Office
Current Status
CofO Issued on 8/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/13/2021 APPLICANT
Assigned to Plan Check Engineer 5/17/2021 CRYSTEL MAALOUF
Corrections Issued 5/17/2021 CRYSTEL MAALOUF
Plan Check Approved 6/14/2021 CRYSTEL MAALOUF
Issued 6/23/2021 APPLICANT
CofO in Progress 7/27/2022 STUART CHAPMAN
Permit Finaled 8/3/2022 DEROLD HAUFF
CofO Issued 8/3/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/20/2021 WALLIE JONG
Sewer availability Cleared 5/20/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 5/26/2021 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/13/2021 Approved STUART CHAPMAN
Footing/Foundation/Slab 8/13/2021 Approved STUART CHAPMAN
Pre-Inspection 8/13/2021 Approved STUART CHAPMAN
Sewer 8/13/2021 Approved STUART CHAPMAN
Underground Mechanical 8/13/2021 Approved STUART CHAPMAN
ELECTRICAL-Rough 9/7/2021 Not Ready for Inspection FREDDIE RIVERA
HVAC-Rough 9/7/2021 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 9/7/2021 Partial Approval FREDDIE RIVERA
Deputy Drilled-In Anchors 9/17/2021 Conditional Approval ALAN MORELOS
BUILDING-Rough-Frame 10/8/2021 Corrections Issued STUART CHAPMAN
Insulation 10/8/2021 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 10/18/2021 Approved STUART CHAPMAN
Insulation 10/18/2021 Corrections Issued STUART CHAPMAN
Drywall Nailing 11/8/2021 Partial Approval STUART CHAPMAN
ELECTRICAL-Final 12/13/2021 Not Ready for Inspection STUART CHAPMAN
HVAC-Final 12/13/2021 Not Ready for Inspection STUART CHAPMAN
HVAC-Rough 12/13/2021 Approved STUART CHAPMAN
Shower Pan 12/13/2021 Approved STUART CHAPMAN
Smoke Detectors 12/13/2021 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 4/15/2022 Approved STUART CHAPMAN
Final 4/15/2022 Corrections Issued STUART CHAPMAN
MERV13>=Final 4/15/2022 Approved STUART CHAPMAN
MERV13>=Rough 4/15/2022 Approved STUART CHAPMAN
PLUMBING-Rough 4/15/2022 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 4/15/2022 SGSOV Not Ready STUART CHAPMAN
Smoke Detectors 4/15/2022 Approved STUART CHAPMAN
Final 6/2/2022 Corrections Issued STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 6/2/2022 SGSOV Approved STUART CHAPMAN
ELECTRICAL-Final 7/27/2022 Approved STUART CHAPMAN
Final 7/27/2022 OK to Issue CofO STUART CHAPMAN
HVAC-Final 7/27/2022 Approved STUART CHAPMAN
PLUMBING-Final 7/27/2022 Approved STUART CHAPMAN
Service/Power Release 7/27/2022 Approved STUART CHAPMAN