315 3/4 S AVENUE 20 90031
Certificate Information: 315 3/4 S AVENUE 20 90031
- Application / Permit
- 21016-10000-12356
- Plan Check / Job No.
- B21LA09075
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 2ND FLOOR OF DUPLEX INTO (N) ATTAHCED ADU WITH AN AREA OF 1026 SQ FT (33' X 37'-7").
- Permit Issued
- Issued on 8/20/2021
- Issuing Office
- Current Status
- CofO Issued on 12/4/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/14/2021 | TSE MING HUANG |
| Corrections Issued | 6/8/2021 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 6/22/2021 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 8/18/2021 | FERNANDO FLORES |
| Plan Check Approved | 8/20/2021 | FERNANDO FLORES |
| Issued | 8/20/2021 | APPLICANT |
| Building Plans Picked Up | 8/23/2021 | APPLICANT |
| CofO in Progress | 11/16/2021 | OSVALDO PARAMO |
| CofO in Progress | 11/16/2021 | OSVALDO PARAMO |
| Permit Finaled | 12/4/2021 | DEROLD HAUFF |
| CofO Issued | 12/4/2021 | DEROLD HAUFF |
| Permit Finaled | 12/4/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 6/7/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 6/11/2021 | RENZ SORIANO |
| Specific Plan | Cleared | 6/15/2021 | OSVALDO GARCIA |
| Address approval | Cleared | 6/23/2021 | RENZ SORIANO |
| Tenant Habitability Plan | Cleared | 7/19/2021 | MICHAEL SOTO |
| Hydrant and Access approval | Cleared | 8/9/2021 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 8/31/2021 | Corrections Issued | OSVALDO PARAMO |
| MERV13>=Rough | 8/31/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 9/8/2021 | Partial Inspection | OSVALDO PARAMO |
| MERV13>=Rough | 9/8/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Wood Frame | 9/16/2021 | Approved | ALAN MORELOS |
| PLUMBING-Rough | 9/17/2021 | Not Ready for Inspection | COREY HUPP |
| PLUMBING-Rough | 9/21/2021 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 9/23/2021 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 9/24/2021 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 9/28/2021 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 10/13/2021 | Approved | OSVALDO PARAMO |
| Final | 10/13/2021 | Corrections Issued | OSVALDO PARAMO |
| MERV13>=Final | 10/13/2021 | Approved | OSVALDO PARAMO |
| MERV13>=Rough | 10/13/2021 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 10/13/2021 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 10/13/2021 | Approved | OSVALDO PARAMO |
| Final | 10/18/2021 | OK to Issue CofO | OSVALDO PARAMO |