1814-1816 1/2 W 22ND ST 90018

Certificate Information: 1814-1816 1/2 W 22ND ST 90018

Application / Permit
21016-10000-12312
Plan Check / Job No.
B21LA09053
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Garage conversion into one story ADU per LAMC 12.22 A33 (c)(d)
Permit Issued
Issued on 10/23/2021
Issuing Office
Current Status
CofO Issued on 10/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/6/2021 APPLICANT
Assigned to Plan Check Engineer 7/8/2021 RAMA DABADGE
Corrections Issued 7/8/2021 RAMA DABADGE
Applicant returned to address corrections 8/11/2021 RAMA DABADGE
Plan Check Approved 10/18/2021 RICARDO RAMIREZ
Issued 10/23/2021 APPLICANT
Building Plans Picked Up 10/27/2021 APPLICANT
CofO in Progress 9/27/2023 ALIZAH MAYAGOITIA
CofO Issued 10/4/2023 DEROLD HAUFF
Permit Finaled 10/4/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/16/2021 CECILIO NAVARRO
Sewer availability Cleared 7/16/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 7/21/2021 CECILIO NAVARRO
Community Plan Implem. Overlay Cleared 9/13/2021 RAFAEL FONTES
ZI Cleared 9/13/2021 RAFAEL FONTES
Tenant Habitability Plan Cleared 10/6/2021 RICHARD BRINSON

Contact Information

No Data Available.

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/8/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Footing/Foundation/Slab 11/8/2021 Corrections Issued KATHRYN BUTTERWORTH
PLUMBING-Rough 11/8/2021 Partial Approval KATHRYN BUTTERWORTH
Footing/Foundation/Slab 11/10/2021 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 12/6/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Rough 12/6/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
MERV13>=Rough 12/6/2021 Approved KATHRYN BUTTERWORTH
METHANE-Rough 12/6/2021 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 12/6/2021 Approved KATHRYN BUTTERWORTH
Sewer 12/6/2021 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Rough 12/9/2021 Corrections Issued KATHRYN BUTTERWORTH
HVAC-Rough 12/9/2021 Approved KATHRYN BUTTERWORTH
Gas Test 2/3/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Rough 3/23/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Footing/Foundation/Slab 3/23/2022 Approved KATHRYN BUTTERWORTH
Underground Mechanical 3/23/2022 Partial Approval KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 4/1/2022 Corrections Issued KATHRYN BUTTERWORTH
ELECTRICAL-Rough 4/1/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Special/Order Compliance 8/30/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Rough 10/19/2022 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Rough 12/5/2022 Approved KATHRYN BUTTERWORTH
HVAC-Rough 12/5/2022 Approved KATHRYN BUTTERWORTH
Underground Mechanical 12/5/2022 Partial Approval KATHRYN BUTTERWORTH
ELECTRICAL-Rough 1/3/2023 Partial Inspection RICHARD DOCKUS
BUILDING-Rough-Frame 1/31/2023 Approved KATHRYN BUTTERWORTH
HVAC-Rough 2/16/2023 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 2/16/2023 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 2/16/2023 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 2/22/2023 Approved STUART CHAPMAN
Gas Test 3/21/2023 Approved KATHRYN BUTTERWORTH
Shower Pan 3/21/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 5/31/2023 Corrections Issued SCOTT FINNILA
Gas Test 5/31/2023 Approved SCOTT FINNILA
MERV13>=Final 5/31/2023 Approved SCOTT FINNILA
Smoke Detectors 5/31/2023 Approved SCOTT FINNILA
Final 8/22/2023 Corrections Issued KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 8/22/2023 SGSOV Not Ready KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 9/5/2023 SGSOV Not Ready KATHRYN BUTTERWORTH
Final 9/13/2023 Corrections Issued KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 9/13/2023 SGSOV Approved KATHRYN BUTTERWORTH
ELECTRICAL-Final 9/26/2023 Approved ALIZAH MAYAGOITIA
Final 9/26/2023 Conditional Approval ALIZAH MAYAGOITIA
Service/Power Release 9/26/2023 Approved ALIZAH MAYAGOITIA
Final 9/27/2023 OK to Issue CofO ALIZAH MAYAGOITIA