627 W 30TH ST 90007
Certificate Information: 627 W 30TH ST 90007
- Application / Permit
- 21016-10000-12212
- Plan Check / Job No.
- B21LA09010
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODELILNG TO CREATE ADDITIONAL BATHROOM AND REMODEL TO KITCHEN.
- Permit Issued
- Issued on 10/1/2021
- Issuing Office
- Current Status
- Permit Finaled on 7/30/2022
Permit Application Status History
| Submitted | 5/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/14/2021 | RICARDO RAMIREZ |
| Corrections Issued | 5/15/2021 | RICARDO RAMIREZ |
| Building Plans Picked Up | 6/7/2021 | APPLICANT |
| Plan Check Approved | 9/1/2021 | DANIEL SANJUAN |
| Issued | 10/1/2021 | APPLICANT |
| Permit Finaled | 7/29/2022 | ALEJANDRO DE ARTOLA |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 7/21/2021 | JEFFREY BULL |
| ZI | Cleared | 7/26/2021 | RICHARD REASER |
| Historic Resource Verification | Cleared | 8/9/2021 | MICAELA TORRES-GIL |
| Redevelopment Project Area | Cleared | 8/13/2021 | DAVID URITA |
| ZI | Cleared | 8/13/2021 | DAVID URITA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/19/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 12/13/2021 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 1/20/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 2/7/2022 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 2/7/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 2/9/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 2/16/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 3/17/2022 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 3/17/2022 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 3/17/2022 | Approved | ALEJANDRO DE ARTOLA |
| MERV13>=Rough | 3/17/2022 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 3/17/2022 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 7/13/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 7/13/2022 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 7/27/2022 | Approved | ALEJANDRO DE ARTOLA |
| Final | 7/27/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| MERV13>=Final | 7/27/2022 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 7/27/2022 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 7/27/2022 | Approved | ALEJANDRO DE ARTOLA |
| Final | 7/29/2022 | Permit Finaled | ALEJANDRO DE ARTOLA |
| HVAC-Final | 7/29/2022 | Approved | ALEJANDRO DE ARTOLA |