623-623 3/4 W 30TH ST 90007

Certificate Information: 623-623 3/4 W 30TH ST 90007

Application / Permit
21016-10000-12169
Plan Check / Job No.
B21LA08985
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
INTERIOR REMODEL AND CONVERT PORTION OF (E) DUPLEX [623-623 1/2 W 30th St] TO ACCESSORY DWELLING UNIT [623 3/4 W 30th St] PER 12.22.A.33(c)&(e).
Permit Issued
Issued on 10/27/2021
Issuing Office
Current Status
CofO Issued on 8/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/13/2021 APPLICANT
Assigned to Plan Check Engineer 5/14/2021 FARSHAD ALIMOHAMADI
Corrections Issued 5/14/2021 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 8/28/2021 STANLEY RAAP
Applicant returned to address corrections 8/30/2021 STANLEY RAAP
Plan Check Approved 10/6/2021 GEORGE ALVAREZ
Issued 10/27/2021 APPLICANT
Building Plans Picked Up 11/1/2021 APPLICANT
CofO in Progress 7/29/2022 ALEJANDRO DE ARTOLA
CofO Issued 8/3/2022 DEROLD HAUFF
Permit Finaled 8/3/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/21/2021 RENZ SORIANO
Tenant Habitability Plan Cleared 7/21/2021 JEFFREY BULL
Sewer availability Cleared 7/23/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 7/26/2021 RENZ SORIANO
Supp. Use District POD/CDO/TDO Cleared 7/26/2021 RICHARD REASER
Historic Resource Verification Cleared 8/9/2021 MICAELA TORRES-GIL
Redevelopment Project Area Cleared 8/13/2021 DAVID URITA
Construction near power lines Cleared 9/30/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/19/2021 Partial Approval ALEJANDRO DE ARTOLA
Deputy Drilled-In Anchors 12/7/2021 Conditional Approval ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 12/13/2021 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 2/8/2022 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 3/18/2022 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 3/18/2022 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 3/18/2022 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 3/18/2022 Approved ALEJANDRO DE ARTOLA
Insulation 3/23/2022 Approved ALEJANDRO DE ARTOLA
Wood Frame 3/23/2022 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 4/1/2022 Approved ALEJANDRO DE ARTOLA
Sewer 4/1/2022 Approved ALEJANDRO DE ARTOLA
Gas Test 5/2/2022 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 5/2/2022 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 5/16/2022 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Final 7/1/2022 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 7/8/2022 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 7/8/2022 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 7/8/2022 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 7/25/2022 Approved ALEJANDRO DE ARTOLA
Final 7/25/2022 Corrections Issued ALEJANDRO DE ARTOLA
MERV13>=Final 7/25/2022 Approved ALEJANDRO DE ARTOLA
MERV13>=Rough 7/25/2022 Approved ALEJANDRO DE ARTOLA
METHANE-Final 7/25/2022 Approved ALEJANDRO DE ARTOLA
METHANE-Rough 7/25/2022 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 7/25/2022 SGSOV Approved ALEJANDRO DE ARTOLA
Smoke Detectors 7/25/2022 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 7/28/2022 Approved ALEJANDRO DE ARTOLA
Final 7/28/2022 OK to Issue CofO ALEJANDRO DE ARTOLA
HVAC-Final 7/28/2022 Approved ALEJANDRO DE ARTOLA