2140 1/2 S 3RD AVE 90018
Certificate Information: 2140 1/2 S 3RD AVE 90018
- Application / Permit
- 21016-10000-12130
- Plan Check / Job No.
- B21LA08955
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan ADU conversion. Convert existing detached garage (598 sf) to accessory dwelling unit per GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 2/22/2022
- Issuing Office
- Current Status
- CofO Issued on 9/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2021 | ZAW HAN |
| Corrections Issued | 5/13/2021 | ZAW HAN |
| Applicant returned to address corrections | 8/19/2021 | ZAW HAN |
| Plan Check Approved | 9/8/2021 | ZAW HAN |
| Issued | 2/22/2022 | APPLICANT |
| CofO in Progress | 9/12/2022 | STUART CHAPMAN |
| Permit Finaled | 9/16/2022 | DEROLD HAUFF |
| CofO Issued | 9/16/2022 | DEROLD HAUFF |
| Permit Finaled | 9/16/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/19/2021 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 5/19/2021 | JEANIE LAM |
| Sewer availability | Cleared | 5/19/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 6/22/2021 | JEANIE LAM |
| Community Plan Implem. Overlay | Cleared | 8/31/2021 | KYLE WINSTON |
| ZI | Cleared | 8/31/2021 | KYLE WINSTON |
Contact Information
| Contractor | Builder Point Construction; Lic. No.: 1059885-B | 11445 PARAMOUNT BLVD SUITE H DOWNEY, CA 90241 |
| Engineer | Rhee,, Kyle; Lic. No.: NA78215 | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/11/2022 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 3/22/2022 | Corrections Issued | STUART CHAPMAN |
| Green Building Rough | 4/21/2022 | Not Ready for Inspection | STUART CHAPMAN |
| METHANE-Rough | 4/21/2022 | Approved | STUART CHAPMAN |
| Wood Frame | 4/21/2022 | Approved | STUART CHAPMAN |
| Smoke Detectors | 4/26/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Insulation | 5/3/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Insulation | 5/5/2022 | Approved | STUART CHAPMAN |
| Drywall Nailing | 5/9/2022 | Approved | STUART CHAPMAN |
| Final | 7/15/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Green Building Final | 7/15/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Green Building Rough | 7/15/2022 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 7/15/2022 | SGSOV Not Ready | STUART CHAPMAN |
| Smoke Detectors | 7/15/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Wood Frame | 7/15/2022 | Approved | STUART CHAPMAN |
| Final | 8/1/2022 | Partial Approval | STUART CHAPMAN |
| Green Building Final | 8/1/2022 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 8/1/2022 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 8/1/2022 | Approved | STUART CHAPMAN |
| Final | 9/12/2022 | OK to Issue CofO | STUART CHAPMAN |