406 1/4 N KENMORE AVE 90004
Certificate Information: 406 1/4 N KENMORE AVE 90004
- Application / Permit
- 21016-10000-12095
- Plan Check / Job No.
- B21LA08925
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT GARAGE TO ADU TO (E) DUPLEX. See Comments.
- Permit Issued
- Issued on 3/25/2022
- Issuing Office
- Current Status
- CofO Issued on 7/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2021 | FERNANDO FLORES |
| Corrections Issued | 6/7/2021 | FERNANDO FLORES |
| Applicant returned to address corrections | 7/31/2021 | FERNANDO FLORES |
| Applicant returned to address corrections | 1/23/2022 | ZAW HAN |
| Building Plans Picked Up | 3/11/2022 | APPLICANT |
| Plan Check Approved | 3/21/2022 | FERNANDO FLORES |
| Issued | 3/25/2022 | APPLICANT |
| CofO in Progress | 7/14/2022 | FREDDIE RIVERA |
| No Progress | 7/22/2022 | RUBEN SALAS |
| CofO in Progress | 7/25/2022 | RUBEN SALAS |
| Permit Finaled | 7/27/2022 | DEROLD HAUFF |
| CofO Issued | 7/27/2022 | DEROLD HAUFF |
| Permit Finaled | 7/27/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/28/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 6/28/2021 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2021 | STEVE MELGAR |
Contact Information
| Contractor | Inhance Construction Inc; Lic. No.: 1073871-B | 7257 BEVERLY RD STE 205 LOS ANGELES, CA 90036 |
| Engineer | Pinzon,, Eduardo A; Lic. No.: C74869 | 821 W SPRUCE ST WEST COVINA, CA 91790 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/14/2022 | Approved | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 4/14/2022 | Approved | FREDDIE RIVERA |
| Wood Frame | 4/14/2022 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 4/25/2022 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 4/27/2022 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 5/9/2022 | Approved | FREDDIE RIVERA |
| FLOOD-Proofing Certificate | 5/9/2022 | Approved | FREDDIE RIVERA |
| Green Building Rough | 5/9/2022 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 5/9/2022 | Approved | FREDDIE RIVERA |
| Insulation | 5/9/2022 | Approved | FREDDIE RIVERA |
| METHANE-Rough | 5/9/2022 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 5/10/2022 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 5/10/2022 | Approved | FREDDIE RIVERA |
| Shower Pan | 5/10/2022 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 6/7/2022 | Approved | FREDDIE RIVERA |
| Final | 6/7/2022 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 6/7/2022 | Partial Inspection | FREDDIE RIVERA |
| HVAC-Final | 6/7/2022 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Final | 6/7/2022 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 6/7/2022 | SGSOV Approved | FREDDIE RIVERA |
| Smoke Detectors | 6/7/2022 | Approved | FREDDIE RIVERA |
| Final | 6/10/2022 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 6/10/2022 | Partial Inspection | FREDDIE RIVERA |
| HVAC-Final | 6/10/2022 | Partial Inspection | FREDDIE RIVERA |
| Green Building Final | 7/5/2022 | Conditional Approval | FREDDIE RIVERA |
| Final | 7/13/2022 | OK to Issue CofO | FREDDIE RIVERA |
| Green Building Final | 7/13/2022 | Approved | FREDDIE RIVERA |
| HVAC-Final | 7/13/2022 | Approved | FREDDIE RIVERA |
| Special/Order Compliance | 7/15/2022 | Partial Inspection | FREDDIE RIVERA |